Building Construction
MinnesotaProvided analysis and review of delay claims that a contractor submitted due to soil contamination caused by underground gasoline tanks on a federal courthouse project.
PROJECT EXPERIENCE
Provided analysis and review of delay claims that a contractor submitted due to soil contamination caused by underground gasoline tanks on a federal courthouse project.
On behalf of an owner, evaluated a contractor’s claim on a new airport terminal building project.
On behalf of an owner, evaluated delayed engineering that affected the timely delivery of construction work packages to the construction contractors on the pipeline and gas recovery facilities associated with an LNG facility.
On behalf of an owner, performed a detailed schedule quality assurance review of the engineering, procurement, construction, commissioning and start-up activities of a central processing facility (CPF). The CPF consisted of utilities, inlet separation, two oil trains, associated gas compressors, natural gas liquids and injection gas units. Identified logic problems and overuse of constraints, which made the indicated critical and near-critical paths questionable.
On behalf of a contractor, analyzed an EPC contractor’s change order and delay claims on a chemical plant project.
The project involved the EPC of a greenfield LNG terminal including major berthing facilities and onshore storage, processing, and pumping services. Provided lead contract and claims support to the joint venture EPC contractor to ensure recovery of owner-caused impacts throughout the construction process. This involved managing and defending a major claim from the international earthworks subcontractor through litigation proceedings in both the U.S. and Mexico. The scope of work further involved detailed rebuttal of schedule, disruption, and damages analyses.
Provided construction claims management services for the owner of a hydroelectric transmission line project. The CAD$4.6 billion transmission line project included a 1,384 km, 500‑kV HVDC transmission line, two new converter stations, and additional 230-kV transmission line interconnections.
Prepared an owner/operator’s claim against a major railroad for causing delays and cost overruns during the construction of fiber optic communications systems along the railroad’s right-of-ways. Developed schedule delay analysis of each of the right-of-ways along which the fiber optic cable was installed in trenches. Identified detailed daily documentation that identified railroad interference or lack of support for the installation of the work.
On behalf of an owner, analyzed a Russian and Turkish contractor’s claim for change orders, delay, and loss of productivity, and the owner’s counterclaims for default due to inadequate project management performance and substandard installations of a residential community project. Developed a document database, inspected the site, reviewed contractual entitlements, and provided the owner with a basis for negotiating a settlement with the contractor.
Performed an analysis in support of an owner’s claim against an international EPC contractor’s performance, delays, and $100 million cost overrun regarding a Spar production facility that was fabricated in Finland for installation in the Gulf of Mexico. Issues involved material delays, welding rework, quadrupling of labor man-hours, wet mating of hard and soft tank/truss, delay, liquidated damages, conversion of contract issues, and related damages.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.