PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Power

Ohio

The mechanical subcontractor executed a contract with a power contractor to complete outage work and repowering of CFB Unit #1. The power contractor caused project delays and interferences that delayed the required work to a period outside of the specified outage period and resulted in a shortage of manpower. The mechanical subcontractor accelerated work to maintain the work planned for the outage period. This required additional coordination of utilities and steam blows and functional tests of fuel system, oil-fired burners, CFB boiler, air ducts, flue gas system and stack, feed water systems, etc. Engaged to provide claims review services. Evaluated owner and contractor claims, including a review of the CPM schedule submittals. Produced a schedule delay and productivity analysis to determine responsibility for project delays. The claims team found that power contractor delays and interferences were primarily responsible for the acceleration effort and difficulties experienced by the mechanical subcontractor during the mechanical completion and operational testing phases of work.

Industrial and Manufacturing

Illinois

Prepared damages analyses on a dispute on a steel mill expansion project. Responsible for a unit price variance analysis and estimating costs for civil, concrete, mechanical, and electric work.

Transportation

Alberta, Canada

On behalf of a contractor, analyzed cost overruns associated with the construction of a heavy haul road in Alberta.

Power

Tennessee

On behalf of a mechanical contractor, analyzed an $11 million claim against an engineering and construction contractor involving the installation of new pollution control equipment on a power plant project.

Gas, Gasification, GTL, LNG, and NGL

Louisiana

On behalf of an owner, reviewed the EPC contract and the project management and project controls procedures for risk identification issues. Provided a claims management and prevention seminar. Also reviewed the EPC contractor's baseline schedule to identify logic and other problems.

Water, Wastewater, Dams, and Marine

Virginia

On behalf of a contractor, prepared an expert report in response to the Sewer Authority’s estimate of potential costs of completing work items that were alleged to be incomplete or defective.

Transportation

New York

Developed and maintained updates of the Baseline CPM Schedule for the $230 million Brooklyn-Queens Expressway (BQE) project. Provided schedule expertise, project administration, coordination, analysis, and negotiation of all time-related issues. The schedule was resource loaded with 2,840 activities.

Water, Wastewater, Dams, and Marine

Colorado

On behalf of an owner, reviewed a contractor’s expert’s schedule delay analysis and damages claim for a wastewater treatment project.  Reviewed the as-planned and as-built schedules, impacted as-built schedule, delay issues, bid data, labor cost overrun data, damages calculations, and project correspondence.  Prepared observations and findings and a draft letter response from the owner to the contractor regarding claim.

Gas, Gasification, GTL, LNG, and NGL

Algeria

On behalf of an owner, performed a detailed schedule quality assurance review of the engineering, procurement, construction, commissioning and start-up activities of a central processing facility (CPF). The CPF consisted of utilities, inlet separation, two oil trains, associated gas compressors, natural gas liquids and injection gas units. Identified logic problems and overuse of constraints, which made the indicated critical and near-critical paths questionable.

Refineries, Petrochemical, and Chemical

Texas

On behalf of an owner, performed a schedule quality assurance review of an EPCM contractor’s EPC schedule on a new methanol plant.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.