Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Industrial and Manufacturing

Colorado

Prepared an electrical contractor’s claim involving engineering delay, errors and omissions resulting in workarounds and construction delays on the installation of life safety systems and instrumentation and control automation on a silicone chip plant and cleanroom facility in Colorado Springs. Performed a schedule analysis of delay impacts due to engineering rework and added change order work, causing schedule compression and acceleration with trade stacking, overmanning of crews with a shortage of qualified labor causing productivity loss due to overtime fatigue, lack of coordinated drawings, late material delivery, and substandard supervisory management and cost controls by the construction manager.

Power

New York

Provided scheduling support to an estimating team on a $250 million 500 MW power plant project. Developed a pre bid schedule over a 12-month period and multiple proposals through contract award. This project required extensive analysis including resource leveling through the use of resource histograms.

Refineries, Petrochemical, and Chemical

Alberta, Canada

On behalf of an EPC contractor, analyzed change order, delay, and loss of productivity claims on a linear alpha olefin project.

Power

Virginia

Developed the detailed schedule and project control system for a 2x400 MW coal-fueled power plant. Created and maintained an accounting and reporting system to track the financial participation of four consortium partners.

Power

New Brunswick, Canada

On behalf of underwriters, as a result of a potentially insured event, evaluated whether other causes of schedule delay to the shutdown and refueling of a nuclear power plant would have caused concurrent delays to the project. Participated as a member of the Loss Adjuster’s Team of experts concerning a $140 million property damage claim and a $255 million delayed start-up claim. Evaluated Primavera schedules, analyzed opposing expert’s reports, and provided support to loss adjusters, counsel, and underwriters at market meetings.

Building Construction

Georgia

Furnished CPM scheduling service for a building contractor on the High Museum of Art expansion project in Atlanta.

Mining and Mineral Processing

British Columbia, Canada

On behalf of an equipment supplier, evaluated a contractor’s time extension request and delay, disruption, and extra work claim on a coke stacker/reclaimer facility.

Transportation

Mozambique

On behalf of an African country, provided a rebuttal report and testimony in international arbitration regarding a claimant’s alleged value of its lost business opportunity after performing, at its own expense and risk, engineering and project development services for a port and rail project that it was not awarded. Evaluated the class of the claimant’s estimates of the project costs before and after it performed its de-risking of the project to lower project costs and determined that the estimates were inaccurate based on the information that was available to prepare the estimates. Thus, found that the claimant’s alleged project savings and its claim amount were speculative.

Refineries, Petrochemical, and Chemical

Louisiana

On behalf of the operator of a chemical storage facility, evaluated a claim associated with delays and cost overruns caused by scope changes and hurricane impacts. Operator alleged that the cost of the facility significantly increased as a result of owner-caused changes and impacts from Hurricanes Katrina and Rita, and that the owner agreed to compensate the operator for the hurricane impacts. The owner alleged that the operator mismanaged the project and that the delays and cost increases were primarily caused by other problems not related to the hurricanes.

Offshore Oil and Gas

Japan, Angola

On behalf of an owner, analyzed a Japanese contractor’s $35 million change order, delay, and loss of productivity claims on an LPG FPSO project that was fabricated in Japan and installed in Angola.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.