Refineries, Petrochemical, and Chemical
New YorkOn behalf of an owner, analyzed change order claims alleged by an EPC contractor on an ethanol from corn project at an old brewery site.
PROJECT EXPERIENCE
On behalf of an owner, analyzed change order claims alleged by an EPC contractor on an ethanol from corn project at an old brewery site.
Developed and maintained updates of the Baseline CPM Schedule for the $230 million Brooklyn-Queens Expressway (BQE) project. Provided schedule expertise, project administration, coordination, analysis, and negotiation of all time-related issues. The schedule was resource loaded with 2,840 activities.
Provided claims analysis and cost and schedule analyses. Prepared a rebuttal report regarding insurance claims related to defective flue gas desulfurization systems on four coal-fired power plant projects.
On behalf of a contractor, prepared a response to an owner’s experts’ reports for an ICC arbitration in London regarding the reasonableness of a bid estimate and the cost to complete an airport project.
The mechanical subcontractor executed a contract with a power contractor to complete outage work and repowering of CFB Unit #1. The power contractor caused project delays and interferences that delayed the required work to a period outside of the specified outage period and resulted in a shortage of manpower. The mechanical subcontractor accelerated work to maintain the work planned for the outage period. This required additional coordination of utilities and steam blows and functional tests of fuel system, oil-fired burners, CFB boiler, air ducts, flue gas system and stack, feed water systems, etc. Engaged to provide claims review services. Evaluated owner and contractor claims, including a review of the CPM schedule submittals. Produced a schedule delay and productivity analysis to determine responsibility for project delays. The claims team found that power contractor delays and interferences were primarily responsible for the acceleration effort and difficulties experienced by the mechanical subcontractor during the mechanical completion and operational testing phases of work.
Assessed delays concerning the construction of a multi-story residential building in Chicago, Illinois, on behalf of a prime contractor, who was seeking delay and other damages against one of its subcontractors. Provided delay analyses and opinions regarding issues that the contractor identified that caused impacts to the project’s final completion milestones and that the subcontractor allegedly caused. The assessment identified which delays were attributable to the subcontractor’s actions or inactions and quantified the number of days for which the prime contractor was entitled to related damages. Based on the damage categories that the prime contractor identified that it suffered as a result of the delays its subcontractor caused, performed analyses and quantified the overall damage amounts, including direct and indirect costs.
On behalf of an equipment supplier, developed estimates to complete four power plant projects that the contractor left incomplete.
Provided CPM scheduling using Primavera on the $13 million San Marcos Town Center project in San Diego. This project included 2,700 LF of box culvert, a CIP bridge structure, grading, paving, traffic control, and the relocation of utilities including fiber optics. The contractor also relocated railroad tracks with ballast to accommodate construction.
Prepared a mechanical contractor’s $20 million claim for delay, additional work, labor disputes, and loss of productivity regarding a $790 million delayed coker project at the Cerro Negro Oil Upgrading Project. Assisted counsel in the preparation of its briefs and document discovery requests. Prepared an expert report that was intended for witness testimony at ICC arbitration hearings in Geneva, Switzerland; however, the case settled before the hearing was conducted.
On behalf of an electrical contractor, evaluated cost overruns resulting from change orders and extra work claims on a training facility at Fort Carson Air Force Base.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.