Gas, Gasification, GTL, LNG, and NGL
AngolaOn behalf of an owner, analyzed schedule delay claims by a prime contractor on an LNG facility being constructed.
PROJECT EXPERIENCE
On behalf of an owner, analyzed schedule delay claims by a prime contractor on an LNG facility being constructed.
Provided a contractor’s baseline and update schedules, change order request and general site supervision on a cement storage and distribution center in Mobile.
Prepared damages and schedule analyses in support of an owner’s defense against a contractor’s $5 million delay and disruption claim on a fast-track CO2 recovery process plant facility.
Provided scheduling support to the estimating team for the $77 million Highbridge Yard Maintenance Facility. Developed pre-bid schedule and aided in the development of Baseline CPM Schedule. The project consisted of the construction of a 62,000 SF rail car maintenance facility (ten car lengths) with two tracks and the installation of associated maintenance and repair equipment. The facility also included an additional 8,300 SF of office space and employee locker rooms located on the second floor. Other project components included the construction of 35,000 feet of track along with 32 switches and electric substation, as well as an employee station.
On behalf of a paint manufacturer, prepared an expert report refuting an EPC contractor’s claim for delay and disruption allegedly resulting from work associated with removal of lead-containing paint from the process plant modules and platforms of an offshore oil production facility installed in the Gulf of Mexico. Case settled prior to trial. The project also involved the defense against the owner’s delay claim for recovery of lost profits due to the delay to the achievement of first oil allegedly caused by the lead abatement program. Presented an expert report demonstrating that the project would have been delayed because of concurrent delay by the EPC contractor. Testified in deposition, which resulted in a successful settlement of the dispute.
Provided contract/entitlement analysis and prepared detailed as-planned and as-built schedule analyses for a contractor on a highway construction project in Pennsylvania. Assisted the contractor to prepare a recovery schedule to mitigate construction delays caused by differing site conditions.
On behalf of an owner, performed an assessment of a Change Order Request for Labor Productivity Impacts and Extended General Conditions Cost. The assessment revealed that the contractor did not follow the MCAA instructions on the use of MCAA’s Labor Factors found in MCAA Management Methods Manual Bulletin No. PD2 (Revised 2011). The assessment also identified that the claim for General Conditions Cost was not supported by any schedule analysis and was a total cost claim even though there were numerous executed change orders, which included a 14 percent markup for supervision, quality control, and safety.
Prepared an electrical subcontractor’s claim for delays, extra work, and loss of productivity on the installation of fire alarm, security, and communication systems for the Federal Bureau of Prisons Project in Beaumont. The contractor’s increased costs resulted from delays, changes, field work orders, rework, loss of productivity, and acceleration to the Division 17 installation work. Prepared an expert report, and assisted counsel in the defense of the opposing expert’s deposition, which resulted in a successful settlement of the dispute.
On behalf of an owner, provided litigation support for a nuclear power plant project involving assessment of cost overruns, delays, inadequate QA/QC documentation, and defective electrical and instrumentation installations.
On behalf of the owner of a large petrochemical complex in Louisiana, assessed a scaffolding subcontractor's claim for increased costs on a unit price subcontract where it installed more scaffolding quantities than originally planned and during a longer period due to project delays. Prepared an expert report.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.