PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Building Construction

Colorado

Prepared a report, damage analysis, and schedule analysis on behalf of a subcontractor for a $450,000 change order on the construction of a parking structure with post-tensioned structural concrete. Prepared an as-built “but-for” schedule analysis and calculated claimed costs.

Refineries, Petrochemical, and Chemical

Ohio

Analyzed allegedly defective installations of fiberglass linings in flue gas desulfurization scrubbers in several power plants in the U.S.

Offshore Oil and Gas

Texas, Louisiana

On behalf of a paint manufacturer, prepared an expert report refuting an EPC contractor’s claim for delay and disruption allegedly resulting from work associated with removal of lead-containing paint from the process plant modules and platforms of an offshore oil production facility installed in the Gulf of Mexico. Case settled prior to trial. The project also involved the defense against the owner’s delay claim for recovery of lost profits due to the delay to the achievement of first oil allegedly caused by the lead abatement program. Presented an expert report demonstrating that the project would have been delayed because of concurrent delay by the EPC contractor. Testified in deposition, which resulted in a successful settlement of the dispute.

Oil Sands

Alberta, Canada

On behalf of interested underwriters, performed cost and data analysis and prepared an expert report for an insurance adjuster. The claim related to a fire loss that was the result of a line failure that caused an oil-based thinning agent to leak at a bitumen upgrader settling basin. The loss occurred for one of the largest operators in the Canadian oil sands industry and its joint venture companies. The facility is an embankment dam that was, by volume of construction material, the largest earth structure in the world in 2001.

Refineries, Petrochemical, and Chemical

Trinidad

On behalf of an owner, analyzed a major international contractor’s $22 million delay and disruption claim on a $100 million refinery upgrade project. The project involved new hydrotreater and sulfur recovery units. Prepared a detailed schedule delay analysis and damage analysis and provided mediation testimony, which resulted in a successful settlement of the dispute.

Power

United Kingdom

EPC design build of a 280 MW gas-fired combined cycle power expansion to a refinery brownfield site. Managed and directed contract administration and claims procedures team. Defended and negotiated a series of owner/subcontractor claims against the EPC contractor. Prepared a force majeure weather impact claim.

Transportation

California

Provided pre-bid scheduling using Primavera for the $180 million San Diego International Airport expansion and infrastructure project. Also reviewed and approved the contractor’s schedules. This project included CIP bridge structures, utility relocations, demolition of existing bridge structure, grading and paving for detours and airport parking.

Transportation

Washington DC

Provided support to management team including schedule coordination, review and development of Baseline CPM Schedule for the $62 million New York Avenue Metrorail Station. The project consisted of the construction of a new “drop in” metro station, including all track work and connections.

Refineries, Petrochemical, and Chemical

Trinidad

Performed schedule delay and change order analysis in support of an owner’s defense of a $10.5 million claim on upgrades to piping, boiler and flare facilities in a major international oil refinery.

Refineries, Petrochemical, and Chemical

Venezuela

Prepared a mechanical contractor’s $20 million claim for delay, additional work, labor disputes, and loss of productivity regarding a $790 million delayed coker project at the Cerro Negro Oil Upgrading Project. Assisted counsel in the preparation of its briefs and document discovery requests. Prepared an expert report that was intended for witness testimony at ICC arbitration hearings in Geneva, Switzerland; however, the case settled before the hearing was conducted.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.