Offshore Oil and Gas
TrinidadOn behalf of an owner, evaluated contractors’ claims for delays and cost overruns associated with two offshore gas pipeline projects.
PROJECT EXPERIENCE
On behalf of an owner, evaluated contractors’ claims for delays and cost overruns associated with two offshore gas pipeline projects.
Prepared a damage and schedule analysis on behalf of a general contractor for a $560,000 claim on a new cafeteria building and dormitory renovation project at a youth detention facility in Okeechobee. Was designated as a CPM expert witness for the jury trial and presented preliminary findings at the court-ordered mediation that resulted in a successful settlement.
On behalf of a European/Japanese joint venture EPC firm, evaluated a $75 million claim on a refinery upgrade project. Assessed the technical entitlement of over 100 change orders forming the basis of the claims as well as the schedule analysis to demonstrate entitlement to an extension of time and delay damages. Evaluated the contractor’s methodology for performing its schedule delay analysis and quantum calculations, and its loss of productivity analysis for proof of damages for labor cost overruns.
Reviewed contracts, policies, and procedures related to project controls, change order management, and scheduling requirements for a major U.S. chemical company. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.
On behalf of an owner, analyzed its claim regarding defective designs and installations associated with an offshore gas production facility, pipeline, and onshore gas processing plant. Testified in arbitration.
On behalf of a major U.S. oil company, evaluated potential delay claims from the contractor associated with a DCS and alarm management upgrade to an offshore platform in the North Sea.
On behalf of an owner, performed a comprehensive “cold eyes” contract risk analysis of the EPC contract documentation, including legal and non-legal exhibits and appendices, contained in the ITT. Provided a written list of recommendations with supporting justification of contractual provisions in the ITT that should be amended, deleted, and/or inserted so as to properly mitigate the client’s risk against spurious and/or undue claims/change orders. Also provided written recommendations as to what impact a project-wide incentive program would have on the contract contingency estimates.
On behalf of an owner, participated in the preliminary analysis and evaluations of delay and disruption claims by an EPC contractor on a large LNG project in the southeastern United States. Evaluated multiple EPC contractor delay claim submissions and reports that included calculation of delay costs. The owner used these independent evaluations in pre-mediation discussions and negotiations.
On behalf of an owner, developed cash flow economic evaluation computer models and prepared capital and operating cost estimates and economic analyses used in the negotiation of the $1.1 billion project loan guarantee for a shale oil project.
On behalf of the owner of a large petrochemical complex in Louisiana, assessed a scaffolding subcontractor's claim for increased costs on a unit price subcontract where it installed more scaffolding quantities than originally planned and during a longer period due to project delays. Prepared an expert report.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.