Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Building Construction

Colorado

Prepared a claim involving total cost reconstruction and damages analysis for a resort condominium complex.

Power

Louisiana

On behalf of an owner, provided litigation support for a nuclear power plant project involving assessment of cost overruns, delays, inadequate QA/QC documentation, and defective electrical and instrumentation installations.

Transportation

Colorado

On behalf of an electrical subcontractor, evaluated delays and increased labor costs on the construction of a large highway project in Colorado.

Power

Connecticut

Analyzed a $50 million delayed start-up claim on a 500 MW power plant. Evaluated project delays and cost impacts related to the Heat Recovery Steam Generator (HRSG) collapse.

Building Construction

Texas

Prepared an electrical subcontractor’s claim for delays, extra work, and loss of productivity on the installation of fire alarm, security, and communication systems for the Federal Bureau of Prisons Project in Beaumont. The contractor’s increased costs resulted from delays, changes, field work orders, rework, loss of productivity, and acceleration to the Division 17 installation work. Prepared an expert report, and assisted counsel in the defense of the opposing expert’s deposition, which resulted in a successful settlement of the dispute.

Power

California

The executive management of this EPC contractor desired to make its project financial forecasting more robust after suffering a number of project write-downs. After verifying that these write-downs were more than an accounting exercise, the EPC contractor wanted an independent third party to evaluate its bidding and execution practices, benchmark them against industry practices, and develop an integrated project risk management/project governance system that executive management could rely upon. Engaged to evaluate the written procedures and practices of each of the four divisions against industry practices. After the steps required to make those procedures and practices more robust were defined, the team worked with the client to revise the procedures and adjust its practices to make the output of the bidding and execution processes more reliable and transparent to management. This work also involved developing a client custom project governance program to identify high-risk bids and projects during execution and define the tools/staff needed to address these high-risk situations.

Building Construction

Montana

Performed claims analysis, construction oversight, contract administration, and expert testimony for a surety involved in the mechanical installations on a prison project.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner seeking to recover hundreds of millions of dollars in delay and disruption costs paid to an EPC contractor on an LNG plant, performed the following scope of work: 1) critique of the contractor’s compliance with industry practices in the preparation and updating of the project baseline CPM schedule and schedule updates; 2) preparation of a windows-based schedule delay analysis to quantify delays on the critical and near-critical paths; 3) assessment of delay, disruption, and project management performance issues by the EPC contractor; and 4) quantification of delay and disruption damages incurred by the subcontractors in the construction of the facility. Prepared an expert report to be submitted as part of arbitration proceedings.

Refineries, Petrochemical, and Chemical

Louisiana

On behalf of a contractor, analyzed an EPC contractor’s change order and delay claims on a chemical plant project.

Gas, Gasification, GTL, LNG, and NGL

New Brunswick, Canada

On behalf of an insurance company, analyzed delays related to the construction of an LNG terminal in New Brunswick. The delay analysis included equipment to unload tanker, transfer to LNG storage tanks, vaporization of the LNG, and metering of the gas as it was introduced into a natural gas pipeline. The owner filed the claim because materials were lost overboard at sea in severe weather while being shipped to the site.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.