PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Gas, Gasification, GTL, LNG, and NGL

Nigeria, Germany

On behalf of a major U.S. oil company, evaluated a civil subcontractor’s delay claim regarding foundation and civil works associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Gas, Gasification, GTL, LNG, and NGL

British Columbia, Canada

Provided expert testimony in arbitration, on behalf of the designer and module fabricator, regarding owner claims of faulty workmanship, delayed project completion, increased project costs, and the designer’s counterclaims of unpaid invoices and change orders related to the design and fabrication of modules and the construction of a gas processing facility. Provided deposition testimony regarding an expert witness rebuttal report.

Building Construction

Ontario, Canada

On behalf of an insurance carrier, prepared an expert report for a case before the Superior Court of Ontario pertaining to the cost of construction to complete a residence in Metcalfe, Ontario, Canada. Reviewed, analyzed, and commented on the plaintiff’s expert report. Developed an estimated construction cost analysis for the scope of work presented by plaintiff’s expert. Opined on whether individual scopes of work provided by the plaintiff were a part of the completion of the house or an enhancement of the house.

Offshore Oil and Gas

Trinidad

On behalf of an owner, evaluated contractors’ claims for delays and cost overruns associated with two offshore gas pipeline projects.

Power

Rhode Island

EPC design build of a 500 MW gas-fired power plant. The project was significantly delayed and disrupted due to local unavailability of labor resources despite union agreements to provide the required construction manpower. Prepared a force majeure claim based on lack of available local labor and other resources. This involved considerable research into area and regional labor usage, related area and regional construction facilities, and union services interfaces. Submitted a heavily researched paper to the client including supporting CPM analysis and contract entitlements to facilitate settlement negotiations. The main contractor succeeded in recovering additional monies and avoiding liquidated damages.

Transportation

Wyoming

On behalf of the Wyoming Department of Transportation, evaluated a contractor’s delay and extended overhead claims on a structural steel bridge and anchored retaining wall project. Evaluated whether there was a reasonable basis for terminating the contractor.

Refineries, Petrochemical, and Chemical

Texas

Prepared damages and schedule analyses in support of an owner’s defense against a contractor’s $5 million delay and disruption claim on a fast-track CO2 recovery process plant facility.

Pipelines and Utilities

Pennsylvania

On behalf of an owner, analyzed the validity of costs that a contractor invoiced on a pipeline project. Prepared an expert report and testified in trial.

Power

Indonesia

On behalf of an owner, performed an evaluation of the integrity of a contractor’s schedule and analysis of delay and loss of productivity claims associated with the design and construction of a new geothermal power plant. The contractor alleged delays associated with late drawing comments by the owner, customs clearance problems, and scope of work changes. The contractor also alleged that it had to accelerate to overcome the delays. On behalf of the owner, performed schedule quality assurance review studies of the contractor’s submitted Recovery Schedule compared to its Baseline Schedule. Identified and recommended resolution of hundreds of open-end activities, problems with constraints, and critical and near-critical path problems. Also analyzed issues involving the schedule being “at large.”

Building Construction

Colorado

Prepared an expert report regarding disputed change orders, delay, and project management performance on an expansion of a county jail.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.