Transportation
ColoradoPrepared project schedule for the general contractor on a highway construction project, analyzed delays, and prepared written reports for time extension requests to the project owner. Testified in arbitration.
PROJECT EXPERIENCE
Prepared project schedule for the general contractor on a highway construction project, analyzed delays, and prepared written reports for time extension requests to the project owner. Testified in arbitration.
On behalf of an EPCM contractor for the construction of two coal/oil-fired power plant projects in Saudi Arabia, provided claim support services concerning the owner’s denial of payment of final invoices and other costs associated with the EPCM contractor’s consulting works. The owner alleged that the EPCM contractor did not deliver technical documents such as plans, engineering drawings, computer network support services, and additional engineering support services. Supported the legal team’s preparation of the Statement of Claim submitted to the Riyadh Commercial Court concerning the EPCM contractor’s entitlement to additional payment. The court awarded a very favorable settlement to the EPCM contractor.
Retained by the owner of a surfactants expansion project to defend a claim by an electrical contractor for increased costs and loss of productivity. Evaluated standard of care, schedule, causation, labor productivity (including loss productivity due to changes), and damages.
On behalf of an electrical contractor, reviewed the CPM schedule prepared for the construction of the electrical work on the new Denver Broncos Stadium
On behalf of an owner, performed a comprehensive “cold eyes” contract risk analysis of the EPC contract documentation, including legal and non-legal exhibits and appendices, contained in the ITT. Provided a written list of recommendations with supporting justification of contractual provisions in the ITT that should be amended, deleted, and/or inserted so as to properly mitigate the client’s risk against spurious and/or undue claims/change orders. Also provided written recommendations as to what impact a project-wide incentive program would have on the contract contingency estimates.
Developed the Baseline CPM Schedule for the $76 million Route 18 Extension Section 2A Highway Project.
Performed CPM scheduling, pay application, and dispute resolution services for the owner of the E-470 Public Toll Road project in Denver. Tracked and monitored the general contractor’s 5,500-activity CPM schedule that was cost and resource loaded. Provided effective pay application payment services by verifying and approving work performed by the general contractor. Performed various special studies regarding disputed pay items as well as the calculations of projected future value of interest for disputed work. Successfully worked with the contractor’s schedulers to develop an effective procedure for schedule updates and changes.
As part of the claim scheduling team, provided support documentation, presentation, and negotiation for a $30 million claim on the $400 million Boston Central Artery Project “Big Dig.”
Prepared a schedule delay analysis for an underground piping subcontractor. Was designated as a CPM scheduling expert. The claim settled in negotiations after preparation of an expert report.
On behalf of an owner, prepared an expert report regarding the potential impact on the surrounding area caused by the construction and operation of a compressor station project.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.