Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Refineries, Petrochemical, and Chemical

Trinidad

On behalf of the owner of a large petrochemical plant project in Trinidad, evaluated numerous claims totaling US$230 million involving delays, cumulative impact to the project, and whether the project achieved mechanical completion.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner of an LNG plant, assessed an EPC contractor’s expert’s quantification of costs incurred at the module fabrication yards and the contractor’s quantification of its management personnel costs during the delay period. Prepared two expert reports submitted as part of arbitration proceedings.

Power

Finland

On behalf of an owner, evaluated a contractor’s expert report and €18 million delay and disruption claim concerning the replacement of emergency diesel generators on a nuclear power plant in Finland. Assessed the expert’s time extension analysis, which was found to lack an assessment of the critical path of the work. The claim was ultimately rejected.

Building Construction

Colorado

Prepared a contractor’s claims for delays, impacts, and cost overruns experienced during construction of a multi-unit apartment complex.

Transportation

New York

Provided support to management team including schedule coordination, review and development of Baseline CPM Schedule for the $87 million Roosevelt Avenue/74th Street reconstruction project. The schedule was resource loaded with 3,200 activities.

Power

Pennsylvania

Analyzed a contractor’s $8 million delay and disruption claim against the owner of a 2x1 combined cycle power plant in Redding. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Pipelines and Utilities

Colorado

On behalf of an owner, prepared an expert report regarding the potential impact on the surrounding area caused by the construction and operation of a compressor station project.

Gas, Gasification, GTL, LNG, and NGL

Texas

On behalf of a mechanical contractor, prepared a claim for compensable delays due to the owner’s impacts to the contractor’s work. The project scope related to mechanical infrastructure in a natural gas processing facility.

Refineries, Petrochemical, and Chemical

U.S. Virgin Islands

On behalf of a contractor, analyzed its pipe fabrication loss of productivity claim on a project involving an upgrade to an existing refinery.

Power

Ontario, Canada

Assisted an owner in performing its due diligence of cost estimates and schedules by: (a) validating that the estimations of asset management costs were based on a “Class 2” estimate as defined by the Association of Advancement of Cost Engineering International (AACEI) and (b) reviewing refurbishment schedules to ensure that there were no contingencies in the integrated base schedule.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.