Transportation
FloridaPrepared a schedule delay analysis for an underground piping subcontractor. Was designated as a CPM scheduling expert. The claim settled in negotiations after preparation of an expert report.
PROJECT EXPERIENCE
Prepared a schedule delay analysis for an underground piping subcontractor. Was designated as a CPM scheduling expert. The claim settled in negotiations after preparation of an expert report.
The project centered on the contract to design and build a 663 MW sub-critical pulverized coal-fired plant addition to an existing brownfield facility. This was a full EPC contract involving multiple stakeholders including a joint venture between the major contracting entities and power island suppliers. Managed a team engaged to provide risk management and claims avoidance advisory and training services to the on-site project teams. Services also included claims avoidance management both on a term and “as required” basis to facilitate early settlement of project problems and avoid lengthy disputes. The project was completed with no major claims or dispute issues.
On behalf of an owner, performed an evaluation of the integrity of a contractor’s schedule and analysis of delay and loss of productivity claims associated with the design and construction of a new geothermal power plant. The contractor alleged delays associated with late drawing comments by the owner, customs clearance problems, and scope of work changes. The contractor also alleged that it had to accelerate to overcome the delays. On behalf of the owner, performed schedule quality assurance review studies of the contractor’s submitted Recovery Schedule compared to its Baseline Schedule. Identified and recommended resolution of hundreds of open-end activities, problems with constraints, and critical and near-critical path problems. Also analyzed issues involving the schedule being “at large.”
Provided litigation support services on the $75 million Kaiser Hospital complex in Riverside, California. Performed detailed quantity take-offs for earthwork, concrete foundations structures and slabs, metal deck, drywall, chemical fireproofing, marblecrete, glass curtain walls, and storefront. Created a 900-activity as-bid CPM schedule to determine a reasonable project schedule. Developed a 1,100-activity as-built CPM schedule and analyzed actual manpower distribution to evaluate lost productivity issues.
On behalf of an owner of an LNG plant, assessed an EPC contractor’s expert’s quantification of costs incurred at the module fabrication yards and the contractor’s quantification of its management personnel costs during the delay period. Prepared two expert reports submitted as part of arbitration proceedings.
Analyzed an owner’s errors and omissions claim against the design contractor on a condensate plant project.
On behalf of the EPCM contractor, performed preliminary standard of care analyses regarding an iron ore mining project involving mining, crushing, and grinding processes and potential variations in each of these processes that may have effected production. Evaluated standard of care, schedule delay, life of mine, and loss of profit issues.
Provided claims analysis services for an insurance company regarding the reconstruction of a natural gas plant in British Columbia following an explosion. Performed a schedule analysis to determine when plant reconstruction could have been completed absent the improvements to the facility that the owner made.
On behalf of an owner, analyzed an $85 million change order and delay claim regarding an offshore Compliant Piled Tower constructed in Texas and topsides facilities fabricated in South Korea for installation offshore Angola.
Provided a claims prevention training seminar for the National Gas Company.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.