Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Refineries, Petrochemical, and Chemical

Alberta, Canada

On behalf of an insurance company, analyzed a $50 million loss for property damage and business interruption resulting from cracking to a reactor vessel at a glycol process plant facility in Alberta. Prepared deposition questions and assisted loss adjusters and counsel for the underwriters with cost and schedule analyses.

Building Construction

Minnesota

Provided analysis and review of delay claims that a contractor submitted due to soil contamination caused by underground gasoline tanks on a federal courthouse project.

Building Construction

Colorado

On behalf of Denver Public Schools (DPS), provided CPM schedule and cost analysis and dispute resolution services that defended against unsubstantiated general contractor claims that exceeded $3 million. Participated in the DPS dispute resolution team that resulted in the successfully negotiated settlement of all general contractor claims at a significantly reduced amount.

Mining and Mineral Processing

Manitoba, Canada

Developed a thesis for an Equitable Adjustment. Reviewed existing cost calculations and data and prepared Phase I findings regarding a claim for Equitable Adjustment for a law firm on behalf of a heavy civil contractor regarding the rehabilitation of a mine tailings management area in Manitoba.

Transportation

Colorado

Assisted an owner’s construction manager in the analysis of schedule delay and productivity loss claims submitted by a design-build contractor for the engineering and construction of a roadway project in Colorado. Parties settled prior to arbitration.

Water, Wastewater, Dams, and Marine

Ireland

The project centered on the EPC design/build of a state-of-the-art sewage treatment plant to replace an existing, overutilized facility in order to meet the current and future needs of the city. Due to site constraints, the plant involved stacking SBR’s on top of each other and building the new works parallel to maintaining the old plant prior to demolition. EU environmental regulations were critical to maintaining high standards of odor and treated water outputs. The plant ultimately failed to meet performance standards, was delayed in construction, and had operational issues for the local residential areas. Engaged to provide support in developing the main contractor’s construction claims (in conjunction with the main contractor’s consortium partners) against the owner and assist with resolution of insurance claims for E&O problems during the design process. This involved CPM and disruption analysis, plus coordinating outside counsel and other experts to support the contractor’s position.

Transportation

Florida

Prepared a contractor’s baseline and update schedules on the $100 million Palm Beach International Airport Interchange. Preparation of contractor’s claim against owner due to unforeseen conditions, owner delays, and productivity issues.

Power

Washington

On behalf of a contractor, analyzed schedule delays on a naval facility electrical substation project including: outage delays, switchgear design deficiencies, SCADA design deficiencies, and ground mat deficiencies.

Gas, Gasification, GTL, LNG, and NGL

Texas

On behalf of an LNG buyer seeking to recover hundreds of millions of dollars in lost revenue as a result of a major fire and explosion on an LNG plant, performed the following scope of work: 1) critiqued the owner’s compliance with established best practice and standard of care for the LNG industry; 2) developed Gross Negligence (GN) table identifying deficiencies and inadequacies in the owner’s operations and maintenance practices; the GN table provided the level of technical support needed by the legal team to essentially prepare an informal statement of claim; and 3) provided technical explanations and clarifications as the legal team required.

Transportation

Minnesota

On behalf of a contractor, analyzed damages to rebut a $52 million claim from the owner on a large wastewater tunnel. Audited and reconciled $166 million in actual costs versus an after the fact estimate of $114 million.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.