Power
WashingtonOn behalf of a contractor, analyzed schedule delays on a naval facility electrical substation project including: outage delays, switchgear design deficiencies, SCADA design deficiencies, and ground mat deficiencies.
PROJECT EXPERIENCE
On behalf of a contractor, analyzed schedule delays on a naval facility electrical substation project including: outage delays, switchgear design deficiencies, SCADA design deficiencies, and ground mat deficiencies.
On behalf of an owner, analyzed a Russian and Turkish contractor’s claim for change orders, delay, and loss of productivity, and the owner’s counterclaims for default due to inadequate project management performance and substandard installations of a residential community project. Developed a document database, inspected the site, reviewed contractual entitlements, and provided the owner with a basis for negotiating a settlement with the contractor.
Prepared a mechanical contractor’s $20 million claim for delay, additional work, labor disputes, and loss of productivity regarding a $790 million delayed coker project at the Cerro Negro Oil Upgrading Project. Assisted counsel in the preparation of its briefs and document discovery requests. Prepared an expert report that was intended for witness testimony at ICC arbitration hearings in Geneva, Switzerland; however, the case settled before the hearing was conducted.
On behalf of an owner, analyzed a mechanical contractor’s $7 million marine lien delay and disruption claim against a major oil company on an offshore oil production project. The claim involved the value of equipment, piping, and structural installations on two refurbished rigs.
Analyzed a contractor’s delay and disruption claim against the owner of a 4x2 combined cycle power plant in Athens. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.
On behalf of an equipment supplier, developed estimates to complete four power plant projects that the contractor left incomplete.
Analyzed delay claims and supporting documentation that a contractor submitted for the manufacture of four HRSGs for a repowering project.
On behalf of an owner, analyzed entitlement, schedule delay and damages related to a contractor’s $12 million claim against a major international chemical company associated with the construction of two process units in an existing chemical plant. The initial EPC contractor was terminated and sought recovery of its cost overruns as a result of field change orders. The owner alleged that the work was defective as a result of engineering errors, field installation errors, and welding defects.
Analyzed an electrical and instrumentation subcontractor’s claim on behalf of an EPC contractor regarding a compressor station project. Assessed allegations of schedule impact and acceleration and prepared an expert report that challenged the claims made by the subcontractor’s expert.
On behalf of an owner, analyzed a claim associated with the placement of undersea oil and gas pipelines in the Gulf of Mexico. Prepared an expert report regarding technical issues of entitlement for cost overrun issues and substantiation of the accounting records to support the costs associated with the claim. Testified in arbitration.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.