Refineries, Petrochemical, and Chemical
OhioAnalyzed allegedly defective installations of fiberglass linings in flue gas desulfurization scrubbers in several power plants in the U.S.
PROJECT EXPERIENCE
Analyzed allegedly defective installations of fiberglass linings in flue gas desulfurization scrubbers in several power plants in the U.S.
Analyzed and presented schedule impacts and litigation support services for a public schools district in defense of a general contractor’s claims on four elementary schools.
On behalf of an owner, performed an assessment of a Change Order Request for Labor Productivity Impacts and Extended General Conditions Cost. The assessment revealed that the contractor did not follow the MCAA instructions on the use of MCAA’s Labor Factors found in MCAA Management Methods Manual Bulletin No. PD2 (Revised 2011). The assessment also identified that the claim for General Conditions Cost was not supported by any schedule analysis and was a total cost claim even though there were numerous executed change orders, which included a 14 percent markup for supervision, quality control, and safety.
On behalf of the operator of a chemical storage facility, evaluated a claim associated with delays and cost overruns caused by scope changes and hurricane impacts. Operator alleged that the cost of the facility significantly increased as a result of owner-caused changes and impacts from Hurricanes Katrina and Rita, and that the owner agreed to compensate the operator for the hurricane impacts. The owner alleged that the operator mismanaged the project and that the delays and cost increases were primarily caused by other problems not related to the hurricanes.
Prepared project schedule for the general contractor on a highway construction project, analyzed delays, and prepared written reports for time extension requests to the project owner. Testified in arbitration.
Provided schedule and damages analysis services and prepared a $1.2 million claim for a contractor that built a grocery store. Responsible for auditing and recoding invoices and timesheets, preparing a cost variance analysis and calculating damages, recreating the as-built schedule, and identifying and apportioning delays.
On behalf of an owner, evaluated contractors’ claims for delays and cost overruns associated with two offshore gas pipeline projects.
EPC design build of a 280 MW gas-fired combined cycle power expansion to a refinery brownfield site. Managed and directed contract administration and claims procedures team. Defended and negotiated a series of owner/subcontractor claims against the EPC contractor. Prepared a force majeure weather impact claim.
On behalf of an owner, evaluated a piping module subcontractor’s delay claim associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.
On behalf of a piping manufacturer, analyzed the fabrication of piping components as an element of the fabrication and erection of HRSGs including the identification of aspects of the delay resulting from the actions of the various parties included in the project. Prepared an expert report, which led to settlement of the matter.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.