Water, Wastewater, Dams, and Marine
South CarolinaPrepared entitlement and damage analyses for a hydroelectric pumped storage facility. Performed financial analyses and wrote expert reports.
PROJECT EXPERIENCE
Prepared entitlement and damage analyses for a hydroelectric pumped storage facility. Performed financial analyses and wrote expert reports.
On behalf of an EPC contractor, analyzed change order, delay, and loss of productivity claims on a linear alpha olefin project.
On behalf of an owner, analyzed change order claims alleged by an EPC contractor on an ethanol from corn project at an old brewery site.
Provided a claims prevention training seminar for a contractor that manufactures and installs heat recovery steam generators (HRSG) on power plant projects.
On behalf of an insurance company, analyzed a $500 million claim for business interruption losses due to delays to the startup and commissioning of an upgrader refinery that was built to process synthetic crude oil from an oil sands production facility. The delays were allegedly caused by a fire at the oil sands production mine site, which delayed the transport of bitumen to the refinery through a 200-plus-mile pipeline. Prepared detailed CPM schedule analyses and an expert witness report. Designated as a CPM expert witness in support of the ICC arbitration in Alberta.
On behalf of an owner, reviewed an EPC contractor’s $12 million force majeure delay claim due to heavy rain and flooding. Provided schedule delay analysis services related to the 404 MW combined cycle gas turbine power plant. Scope of work included review and analysis of the EPC contractor's extension of time claim and preparation of the client's response.
Provided damages analysis to rebut an erection contractor’s $1.6 million claim against a steel fabricator on the Kemper Arena. Analysis was used in a rebuttal report and in cross-examination of the opposing expert.
On behalf of an owner, analyzed its $19 million claim for change orders, delay, and disruption on an EPC project involving an MDI chemical plant. The issues also included interpretation of whether the contract was a reimbursable or unit rate/lump sum price.
Prepared a report, damage analysis, and schedule analysis on behalf of a subcontractor for a $450,000 change order on the construction of a parking structure with post-tensioned structural concrete. Prepared an as-built “but-for” schedule analysis and calculated claimed costs.
Assisted an owner’s construction manager in the analysis of schedule delay and productivity loss claims submitted by a design-build contractor for the engineering and construction of a roadway project in Colorado. Parties settled prior to arbitration.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.