Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Offshore Oil and Gas

Brazil, United Arab Emirates

On behalf of an owner, assessed a contractor’s claims involving change orders, delays, and acceleration regarding the design and installation of the topsides for a deep-sea crude oil FPSO project to be installed in Brazil. Evaluated the contractor’s claims regarding loss of productivity for the refurbishment work of the FPSO vessel and for the topsides installation in Dubai. Also supported the owner in resolving a subsea contractor’s prolongation claim.

Gas, Gasification, GTL, LNG, and NGL

Nigeria, Germany

On behalf of a major U.S. oil company, evaluated a civil subcontractor’s delay claim regarding foundation and civil works associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Transportation

Florida

Prepared monthly progress reports and schedule updates for the preliminary engineering and final civil design of the $600 million Central Florida Light Rail Transit System in Orlando. Developed detailed civil design, construction and system-wide interface schedules.

Gas, Gasification, GTL, LNG, and NGL

Saudi Arabia

On behalf of an owner, performed analyses and prepared expert reports regarding schedule delays and increased costs associated with an EPC contractor’s $138 million claim on a gas plant expansion project. The work involved correction of the contractor’s baseline schedule and schedule updates, assessment of impacts allegedly due to change orders, welding defects, late delivery of drawings by the owner, and contractor performance problems. Prepared time impact and As-Built But-For Schedule Analyses to address time extension entitlement, compensable delay, and loss of productivity. Developed a chronological database and assisted the law firm with witness statements and document disclosure requests. Completed a comparative assessment between the project’s radiography records for the rejected pipe joint welds, and the results that were developed from the owner’s radiography expert’s interpretation of the films. Evaluated the opposing experts’ schedule delay and damages analyses and assessment of responsibilities for project management performance problems. Performed extensive schedule quality assurance review studies of the contractor’s contemporaneous EPC project schedules to ensure that these schedules could be used for delay analysis. Identified and documented numerous problems with open-end activities, overuse of constraints, missing original scope, incorrect as-built dates, missing as-built dates, and missing logic links. The dispute was resolved prior to arbitration.

Pipelines and Utilities

Colorado

On behalf of an owner, prepared an expert report regarding the potential impact on the surrounding area caused by the construction and operation of a compressor station project.

Building Construction

California

Analyzed detailed as-planned and as-built schedules for two state prison projects and a city prison project.

Building Construction

Florida

Furnished CPM scheduling services for a building contractor on multiple $40 million+ high rise condominium complexes in Miami and West Palm Beach.

Power

Illinois

On behalf of a manufacturer of HRSGs, analyzed an EPC contractor’s $35 million claim regarding a lump-sum contract to design and build a gas-fired power plant. Assessed the EPC contractor’s allegations regarding the constructability of the HRSGs and the delay and disruption impact of those problems on its work.

Power

Pennsylvania

Analyzed a contractor’s $8 million delay and disruption claim against the owner of a 2x1 combined cycle power plant in Redding. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Refineries, Petrochemical, and Chemical

Trinidad

On behalf of the owner of a large petrochemical plant project in Trinidad, evaluated numerous claims totaling US$230 million involving delays, cumulative impact to the project, and whether the project achieved mechanical completion.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.