Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Oil Sands

Alberta, Canada

Lead cost and schedule consultant retained by a group of insurance companies to evaluate the reasonableness of a $200 million cost estimate and cost/schedule risks associated with the repair of fire damage to four electrostatic precipitators and enclosures in a large oil sands plant in Alberta. The engagement involved site visits, interviews, and the evaluation of rebuild cost and schedule estimates and supporting documentation, with particular emphasis on assumptions, construction means and methods, labor costs and productivity, field indirect costs, contingency, and expediting and delay costs. Final work products included written reports, which addressed the bases for and reasonableness of the repair schedule and cost estimate, and the cost impact of several expedited repair schedule alternatives, and oral presentations to loss adjusters and insurance company representatives.

Refineries, Petrochemical, and Chemical

Angola

On behalf of an owner, analyzed a contractor’s $11 million claim involving disputed change order work, loss of productivity, late materials deliveries, and other delay events on a new petrochemical plant project. Issues involved customs clearance delays and inadequate project management by the contractor.

Transportation

New York

Provided support to management team including schedule coordination, review and development of Baseline CPM Schedule for the $87 million Roosevelt Avenue/74th Street reconstruction project. The schedule was resource loaded with 3,200 activities.

Industrial and Manufacturing

Maryland

Provided entitlement and damages analyses on an $11 million dispute arising from the construction of a semi-conductor fabrication facility. Prepared issue analyses related to mechanical and piping design changes and performed estimates on mechanical and piping work to analyze cost overruns.

Gas, Gasification, GTL, LNG, and NGL

Nigeria, Germany

On behalf of a major U.S. oil company, evaluated a civil subcontractor’s delay claim regarding foundation and civil works associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of a contractor, evaluated defective design and project management performance problems associated with an offshore underwater gas extraction facility, offshore pipelines, and an onshore gas processing plant. The contractor was a joint venture of the design firm and the underwater pipeline installation company. Under a lump sum turnkey contract, the contractor was responsible for carrying out project design, engineering, procurement, construction and commissioning. The owner terminated the contractor and sought damages recovery.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner of an LNG plant, assessed an EPC contractor’s positions with respect to the eligibility of management personnel entitled to be included in delay costs.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner of an LNG plant, assessed an EPC contractor’s expert’s quantification of costs incurred at the module fabrication yards and the contractor’s quantification of its management personnel costs during the delay period. Prepared two expert reports submitted as part of arbitration proceedings.

Building Construction

Colorado

On behalf of an electrical contractor, reviewed the CPM schedule prepared for the construction of the electrical work on the new Denver Broncos Stadium

Power

Mississippi

Assessed the delays a contractor experienced on a project. Provided delay analyses and opinions regarding issues that the contractor identified that caused impacts to the project final completion milestone and that the owner allegedly caused. The assessment identified which delays were attributable to the owner's actions or inactions and quantified the number of days for which the contractor was entitled to an extension of time.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.