Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Industrial and Manufacturing

Colorado

Prepared an electrical contractor’s claim involving engineering delay, errors and omissions resulting in workarounds and construction delays on the installation of life safety systems and instrumentation and control automation on a silicone chip plant and cleanroom facility in Colorado Springs. Performed a schedule analysis of delay impacts due to engineering rework and added change order work, causing schedule compression and acceleration with trade stacking, overmanning of crews with a shortage of qualified labor causing productivity loss due to overtime fatigue, lack of coordinated drawings, late material delivery, and substandard supervisory management and cost controls by the construction manager.

Gas, Gasification, GTL, LNG, and NGL

British Columbia, Canada

Provided expert testimony in arbitration, on behalf of the designer and module fabricator, regarding owner claims of faulty workmanship, delayed project completion, increased project costs, and the designer’s counterclaims of unpaid invoices and change orders related to the design and fabrication of modules and the construction of a gas processing facility. Provided deposition testimony regarding an expert witness rebuttal report.

Offshore Oil and Gas

Russia

On behalf of an owner, evaluated its position for a claim against the EPCM contractor for mismanagement, cost overruns, and delays on the performance of a cost reimbursable contract to design and build an offshore oil and gas production facility. Performed a schedule and cost variance analysis to identify where delays and cost overruns occurred and the allocated causes for such overruns against the owner and the contractor.

Water, Wastewater, Dams, and Marine

Louisiana

Prepared schedule delay and damages analyses and an expert report on behalf of an electrical subcontractor on claims against a general contractor on two Corps of Engineers lock and dam projects on the Red River.

Transportation

New York

Provided support to management team including schedule coordination, review and development of Baseline CPM Schedule for the $87 million Roosevelt Avenue/74th Street reconstruction project. The schedule was resource loaded with 3,200 activities.

Power

Tennessee

On behalf of a mechanical contractor, analyzed an $11 million claim against an engineering and construction contractor involving the installation of new pollution control equipment on a power plant project.

Building Construction

Colorado

On behalf of a drywall and painting subcontractor, provided analysis and quantification of schedule delay, labor productivity loss, and other damage resulting from change orders on a commercial facility in Colorado. Prepared and submitted an expert report. Parties settled prior to arbitration.

Power

Alberta, Canada

Performed schedule delay expert witness services with respect to a $34 million dispute between an electrical power generator and a consortium of power distributors. Issues involved the analysis of concurrent delay. Services included a delay analysis with respect to a forced outage resulting from an alleged force majeure event. Identified and quantified schedule impacts that resulted from accelerating the start of planned outage work that the power plant operator moved to be in parallel with necessary work associated with the forced outage. Provided testimony that addressed impacts to the outage affected by moving the start of planned outage work to be performed concurrently with forced outage work.

Gas, Gasification, GTL, LNG, and NGL

Georgia

On behalf of an owner, participated in the preliminary analysis and evaluations of delay and disruption claims by an EPC contractor on a large LNG project in the southeastern United States. Evaluated multiple EPC contractor delay claim submissions and reports that included calculation of delay costs. The owner used these independent evaluations in pre-mediation discussions and negotiations.

Transportation

California

On behalf of a contractor, performed quality control and analyzed the reasonableness of schedule delays on a $70 million dispute for a tunnel-boring contract on the Los Angeles metro subway project. Construction of the subway tunnels was delayed by over two years. Identified and apportioned responsibility for the delays.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.