Performed project management audits of a gas-to-liquids facility to assist with evaluating the outstanding engineering and construction scope, assess restructuring of the project management team, and assist with the development of a Request for Proposal for the selection of a project management contractor.

Gas, Gasification, GTL, LNG, and NGL

Trinidad

Performed project management audits of a gas-to-liquids facility to assist with evaluating the outstanding engineering and construction scope, assess restructuring of the project management team, and assist with the development of a Request for Proposal for the selection of a project management contractor.

Gas, Gasification, GTL, LNG, and NGL

Nigeria

On behalf of an owner, performed a comprehensive audit of issues that caused substantial delay and cost overruns on a multibillion-dollar gas-to-liquids processing plant. Issues included evaluation of the man-hour and cost estimate for the project, labor productivity, effect of design changes, assessment of the EPC contractor’s management performance, and government-caused problems. Delays and cost overruns were tied to issues to allocate responsibility of the parties.

Gas, Gasification, GTL, LNG, and NGL

Nigeria, Germany

On behalf of a major U.S. oil company, evaluated a civil subcontractor’s delay claim regarding foundation and civil works associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Gas, Gasification, GTL, LNG, and NGL

Nigeria

On behalf of a major U.S. oil company, analyzed the integrity of a Korean contractor’s EPC schedule regarding logic problems, constraints, and reasonableness of the critical path for a major petrochemical plant project.

Gas, Gasification, GTL, LNG, and NGL

Nigeria

On behalf of an owner, evaluated a piping module subcontractor’s delay claim associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Gas, Gasification, GTL, LNG, and NGL

Nigeria

Evaluated the merits of a schedule delay claim submitted by a pipe fabricator on a GTL project in Nigeria. Also assisted the owner in settlement negotiations.