On behalf of an owner, evaluated delayed engineering that affected the timely delivery of construction work packages to the construction contractors on the pipeline and gas recovery facilities associated with an LNG facility.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner, evaluated delayed engineering that affected the timely delivery of construction work packages to the construction contractors on the pipeline and gas recovery facilities associated with an LNG facility.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner, evaluated the project management performance, schedule delay, and cost overrun issues on an LNG facility. Developed report for evaluation by the owner as to the feasibility of recovery from the EPCM contractor of cost overrun issues on a reimbursable contract. Evaluated the integrity of the CPM schedules and cost reporting by the contractor. Evaluated change order and schedule delay issues that the construction contractors alleged.

Gas, Gasification, GTL, LNG, and NGL

Tanzania

On behalf of the government, evaluated the quality of the CPM schedules prepared by several international oil companies for the development of an LNG facility in Tanzania.

Gas, Gasification, GTL, LNG, and NGL

British Columbia, Canada

On behalf of an owner, provided quality assurance reviews of an EPC contractor’s schedules for an LNG facility.

Gas, Gasification, GTL, LNG, and NGL

Nigeria

On behalf of an owner, performed a comprehensive “cold eyes” contract risk analysis of the EPC contract documentation, including legal and non-legal exhibits and appendices, contained in the ITT. Provided a written list of recommendations with supporting justification of contractual provisions in the ITT that should be amended, deleted, and/or inserted so as to properly mitigate the client’s risk against spurious and/or undue claims/change orders. Also provided written recommendations as to what impact a project-wide incentive program would have on the contract contingency estimates.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner, analyzed rework costs caused by defective engineering and poor project management performance by the EPCM contractor of a LNG facility. Developed a basis for estimating the rework costs and prepared several comprehensive reports that the owner used to facilitate a large settlement against the contractor.