Assisted with the preparation of a contractor’s delay claim for late delivery of owner-supplied piping and equipment; extensive rework on improperly fabricated superheat panels; unrealistic, overzealous, and extra contractual inspections and QA/QC demands by owner personnel; extensive additional work associated with the electrical scope; late and incomplete submittal of necessary design information; and excessive changes to design data subsequent to Issue for Construction drawings particularly for the electrical work.