Refineries, Petrochemical, and Chemical
TexasPrepared damages and schedule analyses in support of an owner’s defense against a contractor’s $5 million delay and disruption claim on a fast-track CO2 recovery process plant facility.
PROJECT EXPERIENCE
Prepared damages and schedule analyses in support of an owner’s defense against a contractor’s $5 million delay and disruption claim on a fast-track CO2 recovery process plant facility.
On behalf of an owner, analyzed the adequacy of a cost estimate and construction risks associated with the upgrade of an LNG facility.
On behalf of the owner of a large petrochemical complex in Louisiana, assessed a scaffolding subcontractor's claim for increased costs on a unit price subcontract where it installed more scaffolding quantities than originally planned and during a longer period due to project delays. Prepared an expert report.
Provided claims prevention training seminars for a mineral processing engineering firm in Denver, Tucson, and Mexico City. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.
On behalf of a structural steel fabrication and erection subcontractor, evaluated the merits of delay claims asserted against the general contractor and delay claims from the general contractor associated with a sports stadium constructed to open prior to the 2024 World Cup soccer tournament in Qatar.
On behalf of the operator of a chemical storage facility, evaluated a claim associated with delays and cost overruns caused by scope changes and hurricane impacts. Operator alleged that the cost of the facility significantly increased as a result of owner-caused changes and impacts from Hurricanes Katrina and Rita, and that the owner agreed to compensate the operator for the hurricane impacts. The owner alleged that the operator mismanaged the project and that the delays and cost increases were primarily caused by other problems not related to the hurricanes.
On behalf of an EPC contractor, analyzed change order, delay, and loss of productivity claims on a linear alpha olefin project.
Furnished CPM scheduling services for a building contractor on a luxury apartment home project in Celebration, Florida.
Provided dispute resolution services for a general contractor in defense of $2.5 million in assessed liquidated damages by the owner of a power plant. Evaluated contemporaneous project records to identify project impacts. Identified and quantified critical path delays and lost productivity impacts caused by the late delivery of equipment and materials, late responses to RFIs, and last-minute changes by the owner’s turbine/generator supplier on a new power plant project. Used retrospective CPM schedule delay analysis methodology to demonstrate delays caused by the identified impacts. CPM schedule delay analysis successfully supported the general contractor’s defense against the owner’s assessment of liquidated damages against the general contractor. The general contractor and owner ultimately reached a negotiated settlement.
On behalf of an electrical contractor, prepared a $1.2 million delay and disruption claim on a new university classroom building project.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.