PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Power

California

Analyzed a contractor’s $0.9 million delay and disruption claim against the owner of a 1x1 peaker power plant in Yuba City. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

Ohio

The mechanical subcontractor executed a contract with a power contractor to complete outage work and repowering of CFB Unit #1. The power contractor caused project delays and interferences that delayed the required work to a period outside of the specified outage period and resulted in a shortage of manpower. The mechanical subcontractor accelerated work to maintain the work planned for the outage period. This required additional coordination of utilities and steam blows and functional tests of fuel system, oil-fired burners, CFB boiler, air ducts, flue gas system and stack, feed water systems, etc. Engaged to provide claims review services. Evaluated owner and contractor claims, including a review of the CPM schedule submittals. Produced a schedule delay and productivity analysis to determine responsibility for project delays. The claims team found that power contractor delays and interferences were primarily responsible for the acceleration effort and difficulties experienced by the mechanical subcontractor during the mechanical completion and operational testing phases of work.

Building Construction

Florida

Analyzed and presented schedule impacts and litigation support services for a public schools district in defense of a general contractor’s claims on four elementary schools.

Building Construction

Ohio

Provided litigation support services for a $3 million real estate development project. Created as-planned and as-built CPM schedules for delay and acceleration evaluations including extensive analysis of weather delays.

Water, Wastewater, Dams, and Marine

Alaska, New Mexico

Analyzed a contractor’s claims against the owners of wastewater treatment plant projects. Issues involved included delay, changes, defective specifications, and loss of productivity.

Refineries, Petrochemical, and Chemical

Wyoming

On behalf of an EPC contractor, evaluated the causes of cost overruns that it incurred during a project to upgrade the coker in a refinery. Although the work was performed under a reimbursable contract, the owner decided not to pay part of the costs due to an alleged agreement to cap the project management costs and fee.

Gas, Gasification, GTL, LNG, and NGL

Texas

Provided a claims prevention training seminar for Woodside Energy.

Building Construction

Alabama

Provided a contractor’s baseline and update schedules, change order request and general site supervision on a cement storage and distribution center in Mobile.

Offshore Oil and Gas

Norway, Gulf of Mexico

On behalf of an owner, evaluated a contractor’s $87 million delay and disruption/loss of productivity claim resulting from alleged design changes to a semi-submersible hull and mooring system project for an offshore oil and gas production facility that was fabricated in Norway for installation in the Gulf of Mexico. Evaluated contractor’s entitlement to unresolved change orders and contractor’s alleged delays associated with owner interference, late owner approvals, ABS approval delays, and out-of-sequence work. Prepared an expert report and testified in arbitration.

Pipelines and Utilities

Louisiana

On behalf of an owner, performed an assessment of a contractor’s performance and construction productivity, an evaluation of the contractor’s target cost to complete a natural gas pipeline project, and quantification of costs associated with removing and replacing defective pipe.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.