Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Pipelines and Utilities

Nigeria

On behalf of an owner, analyzed an EPC contractor’s $43 million claim on behalf of an owner involving hundreds of alleged P&ID changes to the FEED design of a compressor station and pipeline project. Also analyzed resulting delay to the completion of the project, and the technical entitlement to the P&ID changes based on standard industry practice for design development, the owner’s specifications, and the timing of the changes.

Gas, Gasification, GTL, LNG, and NGL

Angola

On behalf of an owner, analyzed schedule delay claims by a prime contractor on an LNG facility being constructed.

Building Construction

Florida

Prepared a damage and schedule analysis on behalf of a general contractor for a $560,000 claim on a new cafeteria building and dormitory renovation project at a youth detention facility in Okeechobee. Was designated as a CPM expert witness for the jury trial and presented preliminary findings at the court-ordered mediation that resulted in a successful settlement.

Industrial and Manufacturing

Washington

Analyzed a Swedish contractor’s delay and disruption claim involving the design and construction of a pulp and paper mill.

Power

Alberta, Canada

Performed schedule delay expert witness services with respect to a $34 million dispute between an electrical power generator and a consortium of power distributors. Issues involved the analysis of concurrent delay. Services included a delay analysis with respect to a forced outage resulting from an alleged force majeure event. Identified and quantified schedule impacts that resulted from accelerating the start of planned outage work that the power plant operator moved to be in parallel with necessary work associated with the forced outage. Provided testimony that addressed impacts to the outage affected by moving the start of planned outage work to be performed concurrently with forced outage work.

Building Construction

Colorado

Provided schedule and damages analysis services and prepared a $1.2 million claim for a contractor that built a grocery store. Responsible for auditing and recoding invoices and timesheets, preparing a cost variance analysis and calculating damages, recreating the as-built schedule, and identifying and apportioning delays.

Power

Texas

Analyzed a contractor’s $8 million delay and disruption claim against the owner of a 4x2 combined cycle power plant in Fairfield. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

New Jersey

Performed schedule delay and damages analyses and prepared an expert report for a subcontractor performing the cooling tower design and construction on a combined cycle power plant project.

Building Construction

Colorado

Prepared a contractor’s baseline schedule and schedule updates for the construction of a $5 million church and related site work.

Power

Florida

Assisted with the preparation of a contractor’s delay claim for late delivery of owner-supplied piping and equipment; extensive rework on improperly fabricated superheat panels; unrealistic, overzealous, and extra contractual inspections and QA/QC demands by owner personnel; extensive additional work associated with the electrical scope; late and incomplete submittal of necessary design information; and excessive changes to design data subsequent to Issue for Construction drawings particularly for the electrical work.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.