PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Refineries, Petrochemical, and Chemical

Russia

Provided technical and project management consulting advice to the project management consultant who represented the owner of a refinery in Russia that was undergoing a revamp. Additional advice included the identification of key performance indicators and EPC contracting issues.

Transportation

Colorado

Prepared project schedule for the general contractor on a highway construction project, analyzed delays, and prepared written reports for time extension requests to the project owner. Testified in arbitration.

Industrial and Manufacturing

Florida

On behalf of an owner, analyzed a $60 million claim from a general contractor related to alleged project delay, increased scope, and loss of labor productivity. The project was for the expansion of an existing cement manufacturing plant in Florida and involved the construction of an additional 2,800-ton-per-day production line from raw material handling through bulk material load out. Performed schedule quality assurance reviews of the contractor’s contemporaneous schedules to correctly quantify project delay and disruption from alleged late delivery of owner equipment. Worked closely with the owner to resolve problems contained within the contractor’s contemporaneous schedules such as open-end activities, overuse of constraints, missing original scope, incorrect as-built dates, missing as-built dates, and missing logic links.

Industrial and Manufacturing

Indiana

On behalf of an owner, provided schedule delay analysis, cost analysis, and litigation support of a $400 million blast furnace and coke oven battery project involving analysis of construction cost and schedule overruns and the adequacy of the engineering design.

Gas, Gasification, GTL, LNG, and NGL

Nigeria

On behalf of an owner, evaluated a piping module subcontractor’s delay claim associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Transportation

California

Provided pre-bid scheduling using Primavera for the $180 million San Diego International Airport expansion and infrastructure project. Also reviewed and approved the contractor’s schedules. This project included CIP bridge structures, utility relocations, demolition of existing bridge structure, grading and paving for detours and airport parking.

Transportation

Nevada

Provided cost and CPM scheduling services on a City of Las Vegas Traffic and Communication project. Developed and monitored resource-loaded completion schedules for the remaining work. Performed a retrospective CPM schedule analysis to prove change order impacts to the critical path of the project. Used activity-based costing techniques to appropriately allocate extended corporate and project overhead costs due to a 6-month suspension period. Performed productivity studies and provided resource and cost projects used for cash flow and cost-to-complete purposes. Successfully performed change order pricing and negotiations ($750K) with the owner for numerous design impacts.

Gas, Gasification, GTL, LNG, and NGL

Algeria

On behalf of an owner, performed a detailed schedule quality assurance review of the engineering, procurement, construction, commissioning and start-up activities of a central processing facility (CPF). The CPF consisted of utilities, inlet separation, two oil trains, associated gas compressors, natural gas liquids and injection gas units. Identified logic problems and overuse of constraints, which made the indicated critical and near-critical paths questionable.

Building Construction

North Dakota

Wrote an expert report for an owner regarding a Construction Manager’s (CM) project management performance on the construction of a new hospital facility. The contract was CM at risk with a guaranteed maximum price contract of $280 million. The project scope consisted of a seven-story acute care tower, two-story base facility, six-story medical office building, underground parking and two-story parking structure, and central energy plant. The project incurred over one year of critical path delay, ultimately resulting in the owner terminating the CM for default.

Building Construction

Colorado

Prepared a claim involving total cost reconstruction and damages analysis for a resort condominium complex.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.