Water, Wastewater, Dams, and Marine
VirginiaOn behalf of a contractor, prepared an expert report in response to the Sewer Authority’s estimate of potential costs of completing work items that were alleged to be incomplete or defective.
PROJECT EXPERIENCE
On behalf of a contractor, prepared an expert report in response to the Sewer Authority’s estimate of potential costs of completing work items that were alleged to be incomplete or defective.
On behalf of an owner, evaluated technical issues associated with the commissioning and start-up of an LNG facility.
On behalf of a contractor, analyzed schedule delays on a naval facility electrical substation project including: outage delays, switchgear design deficiencies, SCADA design deficiencies, and ground mat deficiencies.
On behalf of an owner, analyzed delays, acceleration, change orders, unit rate, and loss of productivity claims totaling $20 million by a major U.S. engineering contractor. Also analyzed counterclaims by a major U.S. chemical company on an ethylene plant project.
Provided CPM scheduling on the Molton section of the $800 million San Joaquin Hills Transportation Corridor project in Irvine. This project had over 100 new CIP bridge structures, miles of driven piles, retaining walls, and storm drains, in addition to over 1 million CY of cut/fill earthwork. The Molton Section “Working Schedule” included 1,544 activities.
Prepared a claim involving total cost reconstruction and damages analysis for a resort condominium complex.
Prepared schedule delay and damages analyses and an expert report on behalf of an electrical subcontractor on claims against a general contractor on two Corps of Engineers lock and dam projects on the Red River.
On behalf of an owner, prepared an expert report defending against a contractor’s claim associated with disputed change orders, delay, and loss of productivity on a new refinery debutanizer unit.
On behalf of an owner, evaluated delays and cost overruns on an insulation manufacturing facility in Alberta. Analyzed schedule and cost data in support of the owner’s $28 million counterclaim against an EPC contractor’s $20 million claim. Testified as CPM schedule and cost expert witnesses for the arbitration.
On behalf of an insurer representing a contractor, prepared an expert report and provided testimony regarding the analysis of an owner’s property damage claim following a fire at an oil terminal, which damaged the tank areas, including associated equipment, piping, electrical and instrumentation. Also evaluated the validity of the owner’s warranty claims that existed prior to the fire and included in the owner’s alleged damages. Prepared an expert report and testified in deposition, which led to a settlement of the dispute.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.