Gas, Gasification, GTL, LNG, and NGL
AngolaOn behalf of an owner, analyzed schedule delay claims by a prime contractor on an LNG facility being constructed.
PROJECT EXPERIENCE
On behalf of an owner, analyzed schedule delay claims by a prime contractor on an LNG facility being constructed.
On behalf of a manufacturer of HRSGs, analyzed an EPC contractor’s $35 million claim regarding a lump-sum contract to design and build a gas-fired power plant. Assessed the EPC contractor’s allegations regarding the constructability of the HRSGs and the delay and disruption impact of those problems on its work.
Provided a contractor’s baseline and update schedules, change order request and general site supervision on a cement storage and distribution center in Mobile.
On behalf of an owner, evaluated delays to the installation of a natural gas pipeline project caused by weather delays, defective pipe, and poor performance by the pipeline contractor.
Performed an extension of time claim review, schedule delay analysis, and forensic planning analysis for a central processing facility to collect gas received from all the concession well fields to be compressed prior to transport via pipeline to the treatment plant. The gas pipeline was 24" in diameter and 370 km in length with a maximum capacity of 10 million Sm3/day.
On behalf of an owner, evaluated the project management performance, schedule delay, and cost overrun issues on an LNG facility. Developed report for evaluation by the owner as to the feasibility of recovery from the EPCM contractor of cost overrun issues on a reimbursable contract. Evaluated the integrity of the CPM schedules and cost reporting by the contractor. Evaluated change order and schedule delay issues that the construction contractors alleged.
Prepared an owner’s claim against an engineering and construction management firm that was terminated for default for defective design work, delays, and cost overruns on a guaranteed maximum price contract to build a commercial-scale chemical plant scaled up from a pilot plant test facility.
On behalf of an owner, performed a schedule quality assurance review of an EPCM contractor’s EPC schedule on a new methanol plant.
Provided entitlement and damages analyses on an $11 million dispute arising from the construction of a semi-conductor fabrication facility. Prepared issue analyses related to mechanical and piping design changes and performed estimates on mechanical and piping work to analyze cost overruns.
On behalf of an equipment supplier, evaluated a contractor’s time extension request and delay, disruption, and extra work claim on a coke stacker/reclaimer facility.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.