Power
IndianaOn behalf of a mechanical contractor, prepared a $1 million claim involving the installation of new low NOx and boiler reheater facilities on a power plant project.
PROJECT EXPERIENCE
On behalf of a mechanical contractor, prepared a $1 million claim involving the installation of new low NOx and boiler reheater facilities on a power plant project.
Furnished CPM scheduling service for a building contractor on the Ft. Gillem Medical Laboratories in Atlanta.
Provided cost and CPM scheduling services on a City of Las Vegas Traffic and Communication project. Developed and monitored resource-loaded completion schedules for the remaining work. Performed a retrospective CPM schedule analysis to prove change order impacts to the critical path of the project. Used activity-based costing techniques to appropriately allocate extended corporate and project overhead costs due to a 6-month suspension period. Performed productivity studies and provided resource and cost projects used for cash flow and cost-to-complete purposes. Successfully performed change order pricing and negotiations ($750K) with the owner for numerous design impacts.
Performed an analysis in support of an owner’s claim against an international EPC contractor’s performance, delays, and $100 million cost overrun regarding a Spar production facility that was fabricated in Finland for installation in the Gulf of Mexico. Issues involved material delays, welding rework, quadrupling of labor man-hours, wet mating of hard and soft tank/truss, delay, liquidated damages, conversion of contract issues, and related damages.
On behalf of an owner, provided schedule delay analysis, cost analysis, and litigation support of a $400 million blast furnace and coke oven battery project involving analysis of construction cost and schedule overruns and the adequacy of the engineering design.
Provided a claims prevention training seminar for a chemical company and its EPCM contractor on an $800 million methanol project
On behalf of an EPC contractor, provided schedule delay analysis as well as contractor scheduling and progress reporting during the execution of a steam supply optimization project consisting of equipment erection and piping fabrication and installation for a package boiler system at a manufacturing facility in Louisiana.
On behalf of an electrical contractor, prepared a $1.2 million delay and disruption claim on a new university classroom building project.
Provided construction claims management services for the owner of a hydroelectric transmission line project. The CAD$4.6 billion transmission line project included a 1,384 km, 500‑kV HVDC transmission line, two new converter stations, and additional 230-kV transmission line interconnections.
On behalf of an LNG buyer seeking to recover hundreds of millions of dollars in lost revenue as a result of a major fire and explosion on an LNG plant, performed the following scope of work: 1) critiqued the owner’s compliance with established best practice and standard of care for the LNG industry; 2) developed Gross Negligence (GN) table identifying deficiencies and inadequacies in the owner’s operations and maintenance practices; the GN table provided the level of technical support needed by the legal team to essentially prepare an informal statement of claim; and 3) provided technical explanations and clarifications as the legal team required.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.