Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Refineries, Petrochemical, and Chemical

Argentina

On behalf of an owner, analyzed a contractor’s delay and loss of productivity claim on the design and construction of a polypropylene project.

Power

Ohio

The mechanical subcontractor executed a contract with a power contractor to complete outage work and repowering of CFB Unit #1. The power contractor caused project delays and interferences that delayed the required work to a period outside of the specified outage period and resulted in a shortage of manpower. The mechanical subcontractor accelerated work to maintain the work planned for the outage period. This required additional coordination of utilities and steam blows and functional tests of fuel system, oil-fired burners, CFB boiler, air ducts, flue gas system and stack, feed water systems, etc. Engaged to provide claims review services. Evaluated owner and contractor claims, including a review of the CPM schedule submittals. Produced a schedule delay and productivity analysis to determine responsibility for project delays. The claims team found that power contractor delays and interferences were primarily responsible for the acceleration effort and difficulties experienced by the mechanical subcontractor during the mechanical completion and operational testing phases of work.

Building Construction

Missouri

On behalf of an electrical contractor, prepared a $6 million delay and disruption claim on the St. Louis Stadium and Convention Center project.

Building Construction

United Arab Emirates

Prepared interior design/fit-out contractor’s delay claim with additional associated costs for five hospitality buildings, a ballroom, a marina, and external works due to construction work delay by the main contractor, the MEP subcontractor, and delay in approvals by the client.

Offshore Oil and Gas

Venezuela

On behalf of a major U.S. oil company, performed an analysis and provided deposition testimony regarding a claim against a contractor for $29 million in improper charges on a reimbursable contract for the fabrication of one offshore gas compression platform and two wellhead platforms.

Mining and Mineral Processing

Mexico

Provided claims prevention training seminars for a mineral processing engineering firm in Denver, Tucson, and Mexico City. Recommended clauses to resolve potential inconsistencies, ambiguities, and conflicts. Prepared clauses for cost and schedule control procedures.

Building Construction

Colorado

Calculated $5 million in direct and consequential damages incurred by an owner due to the late and defective construction of a housing development.

Offshore Oil and Gas

Russia

On behalf of an owner, evaluated its position for a claim against the EPCM contractor for mismanagement, cost overruns, and delays on the performance of a cost reimbursable contract to design and build an offshore oil and gas production facility. Performed a schedule and cost variance analysis to identify where delays and cost overruns occurred and the allocated causes for such overruns against the owner and the contractor.

Water, Wastewater, Dams, and Marine

Ohio

Provided dispute resolution services for the City of Columbus’ wastewater treatment plant Project “88.” Participated in document research and discovery of 160,000 project documents. Created an as-built CPM schedule with over 1,600 activities in order to evaluate alleged delays and impacts. Performed a retrospective CPM schedule delay analysis to determine schedule delays to the critical path as well as project acceleration. Determined the validity of 141 alleged contractor claim issues with a value over $7 million. Scrutinized the cause and effect relationship between alleged impact issues and schedule delays. Assisted in damage calculations and manpower distribution analysis. Based on the team’s analysis of the facts, the City of Columbus successfully negotiated an equitable settlement of claims.

Transportation

Colorado

On behalf of an electrical subcontractor, evaluated delays and increased labor costs on the construction of a large highway project in Colorado.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.