PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Gas, Gasification, GTL, LNG, and NGL

Illinois

Retained by the owner of a natural gas liquids extraction and fractionation plant involved in arbitration with an electrical and instrumentation contractor. Analysis and opinions provided included contract review, determination of breach of contract, delay analysis, and calculation of cost reimbursements owed to the contractor and damages incurred by the owner.

Offshore Oil and Gas

Venezuela

On behalf of a major U.S. oil company, performed an analysis and provided deposition testimony regarding a claim against a contractor for $29 million in improper charges on a reimbursable contract for the fabrication of one offshore gas compression platform and two wellhead platforms.

Gas, Gasification, GTL, LNG, and NGL

Mexico

The project involved the EPC of a greenfield LNG terminal including major berthing facilities and onshore storage, processing, and pumping services. Provided lead contract and claims support to the joint venture EPC contractor to ensure recovery of owner-caused impacts throughout the construction process. This involved managing and defending a major claim from the international earthworks subcontractor through litigation proceedings in both the U.S. and Mexico. The scope of work further involved detailed rebuttal of schedule, disruption, and damages analyses.

Gas, Gasification, GTL, LNG, and NGL

Pennsylvania

Retained by a major U.S. gas generation and distribution company to review existing plans and procedures for change order management and project cost and schedule control. Suggested modifications/enhancements to those plans and procedures and provided templates for the contents of these plans and procedures. Also prepared proforma EPC contracts for lump sum and reimbursable cost work.

Refineries, Petrochemical, and Chemical

Alberta, Canada

On behalf of an insurance company, analyzed a $50 million loss for property damage and business interruption resulting from cracking to a reactor vessel at a glycol process plant facility in Alberta. Prepared deposition questions and assisted loss adjusters and counsel for the underwriters with cost and schedule analyses.

Oil Sands

Alberta, Canada

On behalf of an owner, performed a schedule quality assurance review and schedule risk assessment of the integrated master schedule for a $14 billion oil sands project.

Power

Ohio

The mechanical subcontractor executed a contract with a power contractor to complete outage work and repowering of CFB Unit #1. The power contractor caused project delays and interferences that delayed the required work to a period outside of the specified outage period and resulted in a shortage of manpower. The mechanical subcontractor accelerated work to maintain the work planned for the outage period. This required additional coordination of utilities and steam blows and functional tests of fuel system, oil-fired burners, CFB boiler, air ducts, flue gas system and stack, feed water systems, etc. Engaged to provide claims review services. Evaluated owner and contractor claims, including a review of the CPM schedule submittals. Produced a schedule delay and productivity analysis to determine responsibility for project delays. The claims team found that power contractor delays and interferences were primarily responsible for the acceleration effort and difficulties experienced by the mechanical subcontractor during the mechanical completion and operational testing phases of work.

Transportation

Pennsylvania

Provided contract/entitlement analysis and prepared detailed as-planned and as-built schedule analyses for a contractor on a highway construction project in Pennsylvania. Assisted the contractor to prepare a recovery schedule to mitigate construction delays caused by differing site conditions.

Building Construction

Montana

Performed claims analysis, construction oversight, contract administration, and expert testimony for a surety involved in the mechanical installations on a prison project.

Refineries, Petrochemical, and Chemical

Texas

On behalf of an owner, performed a schedule quality assurance review of an EPCM contractor’s EPC schedule on a new methanol plant.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.