Building Construction
GeorgiaPrepared change order requests and general site supervision on various tilt-up concrete warehouse/office build outs in Atlanta.
PROJECT EXPERIENCE
Prepared change order requests and general site supervision on various tilt-up concrete warehouse/office build outs in Atlanta.
Analyzed a contractor’s $0.9 million delay and disruption claim against the owner of a 1x1 peaker power plant in Yuba City. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.
On behalf of an owner, analyzed a claim associated with the placement of undersea oil and gas pipelines in the Gulf of Mexico. Prepared an expert report regarding technical issues of entitlement for cost overrun issues and substantiation of the accounting records to support the costs associated with the claim. Testified in arbitration.
An EPC contractor designed and supplied two 300 MW Circulating Fluidized Bed (CFB) boilers to replace oil and gas-fired boilers, as well as boiler islands on two units. Engaged to prepare a schedule delay analysis related to a claim filed for an equitable adjustment of the contract price on behalf of the EPC contractor against the owner. The project team later made a presentation for mediation to the owner on the EPC contractor’s behalf.
Analyzed an electrical and instrumentation subcontractor’s claim on behalf of an EPC contractor regarding a compressor station project. Assessed allegations of schedule impact and acceleration and prepared an expert report that challenged the claims made by the subcontractor’s expert.
Analyzed a Swedish contractor’s delay and disruption claim involving the design and construction of a pulp and paper mill.
On behalf of an owner, evaluated delays to the installation of a natural gas pipeline project caused by weather delays, defective pipe, and poor performance by the pipeline contractor.
Prepared main contractor’s delay and disruption claim with additional costs on two of The Pearl Qatar residential towers, Plots 20 and 21, due to change orders issued by the client for finished works. Testified concerning the validity of the delay analysis and the resultant cause-effect on the project contractual milestones and the validity of the additional costs claimed by the main contractor.
Assisted a general contractor in a $2 million dispute with the owner of a 200 MW power plant in New Brunswick. Issues involved increased labor costs associated with late delivery of owner-supplied equipment, late design information, and defective design information. The case was settled during negotiation on terms favorable to the client.
On behalf of a prime contractor, provided technical, scheduling, loss of productivity, and damages analyses in regard to a $30 million dispute related to the engineering and construction of a high-grade gold processing facility. Prepared the prime contractor's claim, reviewed and prepared a pass-through claim for the mechanical subcontractor, and evaluated the owner's counterclaim. Evaluated the status of design at contract award, the quality of owner-supplied equipment, the accuracy of the contractors' bid estimates, and the responsibility and impact of numerous design and construction changes as well as other issues. Evaluated and apportioned responsibility for delay, disruption, and damages among multiple parties. Quantified disruption resulting from cold-weather work, overtime, crowding, shift work, and the cumulative impact of changes. The parties settled prior to court proceedings.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.