Power
ArizonaPrepared a detailed schedule for a 500 MW coal-fueled power plant.
PROJECT EXPERIENCE
Prepared a detailed schedule for a 500 MW coal-fueled power plant.
On behalf of a piping manufacturer, analyzed the fabrication of piping components as an element of the fabrication and erection of HRSGs including the identification of aspects of the delay resulting from the actions of the various parties included in the project. Prepared an expert report, which led to settlement of the matter.
Analyzed entitlement, schedule, and cost issues on litigation arising from a construction manager’s termination of a nuclear demolition contractor. Prepared an affirmative claim valued at $2.3 million and rebutted the contractor’s counterclaim valued at $1.5 million.
Prepared schedule delay and damages analyses and an expert report on behalf of an electrical subcontractor on claims against a general contractor on two Corps of Engineers lock and dam projects on the Red River.
Prepared an owner/operator’s claim against a major railroad for causing delays and cost overruns during the construction of fiber optic communications systems along the railroad’s right-of-ways. Developed schedule delay analysis of each of the right-of-ways along which the fiber optic cable was installed in trenches. Identified detailed daily documentation that identified railroad interference or lack of support for the installation of the work.
On behalf of an electrical contractor, reviewed the CPM schedule prepared for the construction of the electrical work on the new Denver Broncos Stadium
This project involved an evaluation of the schedule at a U.S. refinery following a fire and explosion in 2019 and a dispute between the insurance company and owner concerning a business interruption loss due to the refinery shutdown. We reviewed the relevant documents that described the potential refinery rebuild project scope of work and provided an opinion addressing whether the reconstruction schedule was reasonable. We also determined whether the schedule incorporated the rebuild project scope of work set forth in the rebuild cost estimate. Finally, we provided our opinion regarding considerations the rebuild contractor did not address, adequately or at all, that we believe would have had an impact on the rebuild timeline.
Provided construction claims management services for the owner of a hydroelectric transmission line project. The CAD$4.6 billion transmission line project included a 1,384 km, 500‑kV HVDC transmission line, two new converter stations, and additional 230-kV transmission line interconnections.
Prepared CPM fragnets depicting schedule delays. Analyzed productivity losses on a natural gas liquefaction project.
Provided litigation support for the construction cost overruns and delays for several commercial building projects including a luxury hotel and a major office building.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.