Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Refineries, Petrochemical, and Chemical

New York

On behalf of an owner, reviewed schedule acceleration and delays associated with the construction of an ethanol plant. Issues involved force majeure, changed site conditions, and defective work by an EPC contractor.

Mining and Mineral Processing

British Columbia, Canada

On behalf of an equipment supplier, evaluated a contractor’s time extension request and delay, disruption, and extra work claim on a coke stacker/reclaimer facility.

Building Construction

Texas

Provided litigation support for the construction cost overruns and delays for several commercial building projects including a luxury hotel and a major office building.

Transportation

Florida

Prepared a schedule delay analysis for an underground piping subcontractor. Was designated as a CPM scheduling expert. The claim settled in negotiations after preparation of an expert report.

Refineries, Petrochemical, and Chemical

Spain, Argentina, Netherlands

Provided dispute resolution services in support of a chemical company that was defending against $150 million in impact claims made by a European EPC contractor on several polyethylene terephthalate plants. Participated in the document discovery, research, organization, and coding of over 500,000 project records into an Internet-based document repository. Assisted in answering interrogatories and prepared questions for fact witness depositions. Scrutinized the entitlement of alleged critical path schedule delays due to late and continuous changes, technology changes, late turnover package approvals, weather impacts, and slow agency reviews potentially affecting 15,000 schedule activities. Developed a comprehensive delay allocation model used to quantify and document critical path and concurrent delays affecting the schedules. Correlated issues to schedule activities. Employed a retrospective CPM schedule delay analysis methodology to correctly calculate entitlement for compensable delay costs and evaluate concurrent delays due to approved change orders, fact-based project issues, and weather impacts as supported by project records. Based on the findings, the contractor’s claims were grossly overstated and unsupported; the owner enjoyed a favorable settlement at a small fraction of the total dispute. Performed extensive schedule quality assurance review studies of the contractor’s contemporaneous EPC project schedules to determine if these schedules were fit for delay analysis including identification and resolution of open-end activities, overuse of constraints, incorrect as-built dates, missing as-built dates, missing original scope, and missing logic.

Mining and Mineral Processing

Manitoba, Canada

Developed a thesis for an Equitable Adjustment. Reviewed existing cost calculations and data and prepared Phase I findings regarding a claim for Equitable Adjustment for a law firm on behalf of a heavy civil contractor regarding the rehabilitation of a mine tailings management area in Manitoba.

Building Construction

Florida

Furnished CPM scheduling services for a building contractor on a luxury apartment home project in Celebration, Florida.

Pipelines and Utilities

Tunisia

Performed an extension of time claim review, schedule delay analysis, and forensic planning analysis for a central processing facility to collect gas received from all the concession well fields to be compressed prior to transport via pipeline to the treatment plant. The gas pipeline was 24" in diameter and 370 km in length with a maximum capacity of 10 million Sm3/day.

Refineries, Petrochemical, and Chemical

Louisiana

On behalf of the owner of a large petrochemical complex in Louisiana, assessed a scaffolding subcontractor's claim for increased costs on a unit price subcontract where it installed more scaffolding quantities than originally planned and during a longer period due to project delays. Prepared an expert report.

Building Construction

Illinois

Assessed delays concerning the construction of a multi-story residential building in Chicago, Illinois, on behalf of a prime contractor, who was seeking delay and other damages against one of its subcontractors. Provided delay analyses and opinions regarding issues that the contractor identified that caused impacts to the project’s final completion milestones and that the subcontractor allegedly caused. The assessment identified which delays were attributable to the subcontractor’s actions or inactions and quantified the number of days for which the prime contractor was entitled to related damages. Based on the damage categories that the prime contractor identified that it suffered as a result of the delays its subcontractor caused, performed analyses and quantified the overall damage amounts, including direct and indirect costs.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.