Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Power

Rhode Island

EPC design build of a 500 MW gas-fired power plant. The project was significantly delayed and disrupted due to local unavailability of labor resources despite union agreements to provide the required construction manpower. Prepared a force majeure claim based on lack of available local labor and other resources. This involved considerable research into area and regional labor usage, related area and regional construction facilities, and union services interfaces. Submitted a heavily researched paper to the client including supporting CPM analysis and contract entitlements to facilitate settlement negotiations. The main contractor succeeded in recovering additional monies and avoiding liquidated damages.

Power

Virginia

Developed the detailed schedule and project control system for a 2x400 MW coal-fueled power plant. Created and maintained an accounting and reporting system to track the financial participation of four consortium partners.

Transportation

New York

Provided support to management team including schedule coordination, review and development of Baseline CPM Schedule for the $87 million Roosevelt Avenue/74th Street reconstruction project. The schedule was resource loaded with 3,200 activities.

Power

Florida

An EPC contractor designed and supplied two 300 MW Circulating Fluidized Bed (CFB) boilers to replace oil and gas-fired boilers, as well as boiler islands on two units. Engaged to prepare a schedule delay analysis related to a claim filed for an equitable adjustment of the contract price on behalf of the EPC contractor against the owner. The project team later made a presentation for mediation to the owner on the EPC contractor’s behalf.

Refineries, Petrochemical, and Chemical

Texas

On behalf of an owner, analyzed its $19 million claim for change orders, delay, and disruption on an EPC project involving an MDI chemical plant. The issues also included interpretation of whether the contract was a reimbursable or unit rate/lump sum price.

Mining and Mineral Processing

Newfoundland, Canada

On behalf of an owner, performed a review of an EPC contractor’s project management performance and a schedule delay analysis to allocate responsibility for delays to the engineering, procurement, and construction of a multibillion-dollar nickel processing plant in Newfoundland, Canada.  The primary issue was standard of care and whether the EPC contractor was grossly negligent in its performance.  Prepared expert reports and testified in arbitration.

Oil Sands

Alberta, Canada

On behalf of an insurance company, analyzed a $200 million insurance claim for non traditional coverages resulting from delays and cost overruns on the construction of an oil sands mine facility and upgrader unit in Alberta. Prepared expert witness reports in support of the ICC arbitration.

Refineries, Petrochemical, and Chemical

Texas

Reviewed change orders, schedule delays, and pending disputes between a major U.S. chemical company and its mechanical contractor on a methanol plant in Texas. Advised the client as to its exposure regarding the technical issues involved in these issues for purpose of settlement negotiations.

Refineries, Petrochemical, and Chemical

Colorado

Prepared an owner’s claim against an engineering and construction management firm that was terminated for default for defective design work, delays, and cost overruns on a guaranteed maximum price contract to build a commercial-scale chemical plant scaled up from a pilot plant test facility.

Transportation

Nevada

Provided cost and CPM scheduling services on a City of Las Vegas Traffic and Communication project. Developed and monitored resource-loaded completion schedules for the remaining work. Performed a retrospective CPM schedule analysis to prove change order impacts to the critical path of the project. Used activity-based costing techniques to appropriately allocate extended corporate and project overhead costs due to a 6-month suspension period. Performed productivity studies and provided resource and cost projects used for cash flow and cost-to-complete purposes. Successfully performed change order pricing and negotiations ($750K) with the owner for numerous design impacts.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.