Power
MinnesotaProvided a claims prevention training seminar for a U.S. contractor that specializes in the design and construction of HRSGs.
PROJECT EXPERIENCE
Provided a claims prevention training seminar for a U.S. contractor that specializes in the design and construction of HRSGs.
Furnished CPM scheduling services for a building contractor on multiple $40 million+ high rise condominium complexes in Miami and West Palm Beach.
On behalf of an EPCM contractor for the construction of two coal/oil-fired power plant projects in Saudi Arabia, provided claim support services concerning the owner’s denial of payment of final invoices and other costs associated with the EPCM contractor’s consulting works. The owner alleged that the EPCM contractor did not deliver technical documents such as plans, engineering drawings, computer network support services, and additional engineering support services. Supported the legal team’s preparation of the Statement of Claim submitted to the Riyadh Commercial Court concerning the EPCM contractor’s entitlement to additional payment. The court awarded a very favorable settlement to the EPCM contractor.
On behalf of an owner, evaluated the project management performance, schedule delay, and cost overrun issues on an LNG facility. Developed report for evaluation by the owner as to the feasibility of recovery from the EPCM contractor of cost overrun issues on a reimbursable contract. Evaluated the integrity of the CPM schedules and cost reporting by the contractor. Evaluated change order and schedule delay issues that the construction contractors alleged.
Prepared and analyzed detailed as-planned and as-built schedules to assist an owner defending against contractor claims on a university dormitory project in Riverside.
On behalf of an owner, evaluated a contractor’s expert report and €18 million delay and disruption claim concerning the replacement of emergency diesel generators on a nuclear power plant in Finland. Assessed the expert’s time extension analysis, which was found to lack an assessment of the critical path of the work. The claim was ultimately rejected.
Performed an analysis in support of an owner’s claim against an international EPC contractor’s performance, delays, and $100 million cost overrun regarding a Spar production facility that was fabricated in Finland for installation in the Gulf of Mexico. Issues involved material delays, welding rework, quadrupling of labor man-hours, wet mating of hard and soft tank/truss, delay, liquidated damages, conversion of contract issues, and related damages.
On behalf of a mechanical contractor, prepared a claim for compensable delays due to the owner’s impacts to the contractor’s work. The project scope related to mechanical infrastructure in a natural gas processing facility.
On behalf of an underwriter, evaluated an owner’s property damage claim and delays resulting from heavy rains and flooding on a residential and commercial condominium project.
On behalf of a major U.S. oil company, evaluated potential delay claims from the contractor associated with a DCS and alarm management upgrade to an offshore platform in the North Sea.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.