PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Gas, Gasification, GTL, LNG, and NGL

Nigeria

On behalf of an owner, evaluated a piping module subcontractor’s delay claim associated with a GTL facility. Evaluated the integrity of the subcontractor’s schedules and verified the impact of changes to the subcontractor’s schedule. Participated with the EPC contractor and owner to achieve a settlement of the time extension and cost components of the subcontractor’s claim.

Power

Singapore

The project centered on disputes between a major contractor and a mechanical/electrical subcontractor on alleged delay and disruption impacts during the construction of a 380 MW power facility due to alleged late information, delayed procurement, and changes. Project completion was significantly delayed, and the subcontractor claimed the contractor caused the negative schedule impacts, subsequently submitting a request for an equitable adjustment (REA) and filing for arbitration. Team leader engaged to consult on the main contractor’s defense of the claim both during the contract execution works and the post completion arbitration events. This involved day-to-day contract administration, claims preparation, and overall management of claims team, outside counsel, and experts.

Building Construction

Florida

Prepared a damage and schedule analysis on behalf of a general contractor for a $560,000 claim on a new cafeteria building and dormitory renovation project at a youth detention facility in Okeechobee. Was designated as a CPM expert witness for the jury trial and presented preliminary findings at the court-ordered mediation that resulted in a successful settlement.

Water, Wastewater, Dams, and Marine

Ohio

Provided dispute resolution services for the City of Columbus’ wastewater treatment plant Project “88.” Participated in document research and discovery of 160,000 project documents. Created an as-built CPM schedule with over 1,600 activities in order to evaluate alleged delays and impacts. Performed a retrospective CPM schedule delay analysis to determine schedule delays to the critical path as well as project acceleration. Determined the validity of 141 alleged contractor claim issues with a value over $7 million. Scrutinized the cause and effect relationship between alleged impact issues and schedule delays. Assisted in damage calculations and manpower distribution analysis. Based on the team’s analysis of the facts, the City of Columbus successfully negotiated an equitable settlement of claims.

Building Construction

Missouri

Provided damages analysis to rebut an erection contractor’s $1.6 million claim against a steel fabricator on the Kemper Arena. Analysis was used in a rebuttal report and in cross-examination of the opposing expert.

Transportation

Florida

Prepared a schedule delay analysis for an underground piping subcontractor. Was designated as a CPM scheduling expert. The claim settled in negotiations after preparation of an expert report.

Mining and Mineral Processing

Manitoba, Canada

Developed a thesis for an Equitable Adjustment. Reviewed existing cost calculations and data and prepared Phase I findings regarding a claim for Equitable Adjustment for a law firm on behalf of a heavy civil contractor regarding the rehabilitation of a mine tailings management area in Manitoba.

Building Construction

Qatar

Prepared main contractor’s delay and disruption claim with additional costs on two of The Pearl Qatar residential towers, Plots 20 and 21, due to change orders issued by the client for finished works. Testified concerning the validity of the delay analysis and the resultant cause-effect on the project contractual milestones and the validity of the additional costs claimed by the main contractor.

Transportation

California

On behalf of a contractor, analyzed schedule delays in a $70 million dispute resulting from the construction of subway tunnels that were delayed by over two years. Responsible for identifying and apportioning delays.

Power

Labrador and Newfoundland, Canada

Provided claims prevention and claims analysis, claims management, contract administration, and dispute resolution services on behalf of the owner of a CAD$6.2 billion hydroelectric power and transmission line construction project.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.