PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Pipelines and Utilities

India

On behalf of a compressor manufacturer, analyzed delay and performance problems on a gas compressor/pipeline project resulting in liquidated damages in excess of $50 million. This project involved ICC arbitration in Geneva, Switzerland.

Transportation

England

Prepared a CPM schedule analysis of alleged contractor claims associated with construction upgrades to the London Underground Subway system in support of an ICC arbitration.

Refineries, Petrochemical, and Chemical

Louisiana

On behalf of the operator of a chemical storage facility, evaluated a claim associated with delays and cost overruns caused by scope changes and hurricane impacts. Operator alleged that the cost of the facility significantly increased as a result of owner-caused changes and impacts from Hurricanes Katrina and Rita, and that the owner agreed to compensate the operator for the hurricane impacts. The owner alleged that the operator mismanaged the project and that the delays and cost increases were primarily caused by other problems not related to the hurricanes.

Water, Wastewater, Dams, and Marine

Colorado

On behalf of an owner, reviewed a contractor’s expert’s schedule delay analysis and damages claim for a wastewater treatment project.  Reviewed the as-planned and as-built schedules, impacted as-built schedule, delay issues, bid data, labor cost overrun data, damages calculations, and project correspondence.  Prepared observations and findings and a draft letter response from the owner to the contractor regarding claim.

Industrial and Manufacturing

Indiana

On behalf of an owner, provided schedule delay analysis, cost analysis, and litigation support of a $400 million blast furnace and coke oven battery project involving analysis of construction cost and schedule overruns and the adequacy of the engineering design.

Refineries, Petrochemical, and Chemical

Trinidad

On behalf of an owner, analyzed a Canadian contractor’s $25 million delay and disruption claim against the owner of a refinery. The venue was international arbitration under UNCITRAL arbitration rules. The contractor’s scope of work involved the construction of a new visbreaker unit, modernization of instrumentation facilities, and a revamp of a fluid catalytic cracker oil upgrading process unit. The project further involved the organization of thousands of documents and assessments of alleged delays and disruption impacts identified in change orders, correspondence, meeting minutes, disruption notices, monthly progress reports, and CPM updates. The scope of work also included a detailed CPM schedule analysis and the quantification of damages. Prepared an expert report in international arbitration prior to settlement of the dispute.

Building Construction

California

Provided CPM scheduling using Primavera on the $13 million San Marcos Town Center project in San Diego. This project included 2,700 LF of box culvert, a CIP bridge structure, grading, paving, traffic control, and the relocation of utilities including fiber optics. The contractor also relocated railroad tracks with ballast to accommodate construction.

Gas, Gasification, GTL, LNG, and NGL

Trinidad

Assisted with the development of a project management controls unit for a natural gas company. Prepared written findings and recommendations for establishing a project management controls unit and developing a project management methodology using a stage gate process.

Industrial and Manufacturing

Oregon

Performed an entitlement and schedule analysis on a $60 million dispute arising from a steel mill expansion project. Reviewed RFIs, drawing changes, and change orders to identify and apportion schedule impacts.

Building Construction

Kuwait

Prepared a $45 million claim including delay analysis and damages calculations for an Italian construction firm that constructed two hospitals.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.