PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Power

Algeria

On behalf of an equipment supplier, developed estimates to complete four power plant projects that the contractor left incomplete.

Gas, Gasification, GTL, LNG, and NGL

British Columbia, Canada

Provided expert testimony in arbitration, on behalf of the designer and module fabricator, regarding owner claims of faulty workmanship, delayed project completion, increased project costs, and the designer’s counterclaims of unpaid invoices and change orders related to the design and fabrication of modules and the construction of a gas processing facility. Provided deposition testimony regarding an expert witness rebuttal report.

Building Construction

Kuwait

Prepared a $45 million claim including delay analysis and damages calculations for an Italian construction firm that constructed two hospitals.

Refineries, Petrochemical, and Chemical

Vietnam

On behalf of an owner, assessed delays to overall mechanical completion, delays to initial acceptance, defective works counterclaims, cost reduction claim, elements of technical design, cost and schedule overruns, and Ready For Start-Up (RFSU)/Commissioning delays. Prepared expert reports, expert reply reports, and joint expert reports for tribunal submission. Provided litigation support, including preparation of cross-examination questions, and testified in arbitration hearings.

Refineries, Petrochemical, and Chemical

South Carolina

Reviewed an owner’s contract for the engineering, procurement, and construction of a chemical plant. Recommended changes to project management, scheduling, and project controls provisions to improve the owner’s visibility into the progress reporting on the project. Provided a Claims Prevention Seminar.

Offshore Oil and Gas

Gulf of Mexico

On behalf of a paint manufacturer, prepared an expert report refuting an EPC contractor’s claim for delay and disruption allegedly resulting from work associated with removal of lead-containing paint from the process plant modules and platforms of an offshore oil production facility installed in the Gulf of Mexico. Case settled prior to trial. The project also involved the defense against the owner’s delay claim for recovery of lost profits due to the delay to the achievement of first oil allegedly caused by the lead abatement program. Presented an expert report demonstrating that the project would have been delayed because of concurrent delay by the EPC contractor. Testified in deposition, which resulted in a successful settlement of the dispute.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner, evaluated the project management performance, schedule delay, and cost overrun issues on an LNG facility. Developed report for evaluation by the owner as to the feasibility of recovery from the EPCM contractor of cost overrun issues on a reimbursable contract. Evaluated the integrity of the CPM schedules and cost reporting by the contractor. Evaluated change order and schedule delay issues that the construction contractors alleged.

Refineries, Petrochemical, and Chemical

Trinidad

On behalf of an owner, analyzed a major international contractor’s $22 million delay and disruption claim on a $100 million refinery upgrade project. The project involved new hydrotreater and sulfur recovery units. Prepared a detailed schedule delay analysis and damage analysis and provided mediation testimony, which resulted in a successful settlement of the dispute.

Transportation

Florida

Prepared monthly progress reports and schedule updates for the preliminary engineering and final civil design of the $600 million Central Florida Light Rail Transit System in Orlando. Developed detailed civil design, construction and system-wide interface schedules.

Power

New York

Analyzed a contractor’s delay and disruption claim against the owner of a 4x2 combined cycle power plant in Athens. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.