Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Power

Finland

On behalf of an owner, evaluated a contractor’s expert report and €18 million delay and disruption claim concerning the replacement of emergency diesel generators on a nuclear power plant in Finland. Assessed the expert’s time extension analysis, which was found to lack an assessment of the critical path of the work. The claim was ultimately rejected.

Gas, Gasification, GTL, LNG, and NGL

Australia

On behalf of an owner of an LNG plant, assessed an EPC contractor’s expert’s quantification of costs incurred at the module fabrication yards and the contractor’s quantification of its management personnel costs during the delay period. Prepared two expert reports submitted as part of arbitration proceedings.

Power

Manitoba, Canada

Provided construction claims management services for the owner of a hydroelectric transmission line project. The CAD$4.6 billion transmission line project included a 1,384 km, 500‑kV HVDC transmission line, two new converter stations, and additional 230-kV transmission line interconnections.

Transportation

Colorado

Prepared project schedule for the general contractor on a highway construction project, analyzed delays, and prepared written reports for time extension requests to the project owner. Testified in arbitration.

Industrial and Manufacturing

Florida

Assisted an owner in the defense of a $12 million claim on a project involving the design, delivery and construction of a new cement production line from ore receiving to finish mill and product loadout. The EPC contractor claimed increased costs due to alleged owner-caused delays and disruption arising from late delivery of proprietary design information, materials, and equipment; and impacts to labor productivity due to numerous changes to the work and contractor’s alleged acceleration to overcome delays.

Building Construction

United Arab Emirates

Prepared main contractor’s claim against employer for extension of time for completion with additional payment for the Dubai Maritime City Project. Prepared Statement of Claim for extension of time with quantum for time-related and non-time-related additional costs. The dispute concerned construction delays due to multiple reasons that were attributed to the employer, such as delay in review and approval of submittals, excessive variations, lack of access and obstructions to site, and delay in issuance of IFC drawings.

Power

United Kingdom

EPC design build of a 280 MW gas-fired combined cycle power expansion to a refinery brownfield site. Managed and directed contract administration and claims procedures team. Defended and negotiated a series of owner/subcontractor claims against the EPC contractor. Prepared a force majeure weather impact claim.

Transportation

New York

Provided support to management team including schedule review and development of working schedules and sub-networks for claims purposes on the $90 million NYC Times Square Rehabilitation Project. The schedule was cost and resource loaded and contained 2,823 activities.

Power

Louisiana

Analyzed a contractor’s $9 million delay and disruption claim against the owner of a 4x2 combined cycle power plant in Eunice. The scope of the work included a detailed CPM schedule analysis to determine delay and acceleration responsibility.

Power

Algeria

On behalf of an equipment supplier, developed estimates to complete four power plant projects that the contractor left incomplete.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.