Gas, Gasification, GTL, LNG, and NGL
British Columbia, CanadaOn behalf of an owner, provided quality assurance reviews of an EPC contractor’s schedules for an LNG facility.
PROJECT EXPERIENCE
On behalf of an owner, provided quality assurance reviews of an EPC contractor’s schedules for an LNG facility.
On behalf of an owner, performed a comprehensive audit of issues that caused substantial delay and cost overruns on a multibillion-dollar gas-to-liquids processing plant. Issues included evaluation of the man-hour and cost estimate for the project, labor productivity, effect of design changes, assessment of the EPC contractor’s management performance, and government-caused problems. Delays and cost overruns were tied to issues to allocate responsibility of the parties.
On behalf of an owner, performed a schedule quality assurance review of an EPCM contractor’s EPC schedule on a new methanol plant.
On behalf of an EPC contractor, performed claims analysis, damages assessment, and delay evaluations on a $250 million refinery expansion project involving $20 million in damages. The primary issues included bid error, loss of labor productivity, delay and acceleration.
On behalf of a major international oil company, analyzed the quantum aspects of an EPC contractor’s $130 million delay and changed conditions claim. The claim involved the relocation of a gas processing plant project site after construction had commenced because of the discovery of unfavorable soil conditions. Prepared an expert report and rebuttal expert report and testified in ICC arbitration. The EPC contractor’s claim was denied, and the owner’s liquidated damages claim was upheld.
On behalf of an owner, analyzed a claim associated with the placement of undersea oil and gas pipelines in the Gulf of Mexico. Prepared an expert report regarding technical issues of entitlement for cost overrun issues and substantiation of the accounting records to support the costs associated with the claim. Testified in arbitration.
Furnished CPM scheduling services for a building contractor on the Dade County high school located in Miami.
Assessed delays concerning the construction of a multi-story residential building in Chicago, Illinois, on behalf of a prime contractor, who was seeking delay and other damages against one of its subcontractors. Provided delay analyses and opinions regarding issues that the contractor identified that caused impacts to the project’s final completion milestones and that the subcontractor allegedly caused. The assessment identified which delays were attributable to the subcontractor’s actions or inactions and quantified the number of days for which the prime contractor was entitled to related damages. Based on the damage categories that the prime contractor identified that it suffered as a result of the delays its subcontractor caused, performed analyses and quantified the overall damage amounts, including direct and indirect costs.
Prepared detailed as-planned and as-built schedule analyses for a contractor on an earth-filled dam project in New Mexico. Participated in negotiations between the contractor and the U.S. Bureau of Reclamation that resulted in a $55 million settlement for the contractor.
Prepared detailed as-planned and as-built schedule analyses for a contractor on a dam project. Participated in negotiations between the contractor and the Province of Alberta.
Our experts are ready to help.
Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.