Excavator and bulldozers working on a construction site

PROJECT EXPERIENCE

Experience Matters

Long International serves the global construction industry on projects of all types and sizes, as well as disputes of various complexities.

Filter Results

Industry & Project Type
Locations

Gas, Gasification, GTL, LNG, and NGL

Middle East

On behalf of an owner, evaluated technical issues associated with the commissioning and start-up of an LNG facility.

Transportation

Colorado

Performed CPM scheduling, pay application, and dispute resolution services for the owner of the E-470 Public Toll Road project in Denver. Tracked and monitored the general contractor’s 5,500-activity CPM schedule that was cost and resource loaded. Provided effective pay application payment services by verifying and approving work performed by the general contractor. Performed various special studies regarding disputed pay items as well as the calculations of projected future value of interest for disputed work. Successfully worked with the contractor’s schedulers to develop an effective procedure for schedule updates and changes.

Gas, Gasification, GTL, LNG, and NGL

Wyoming

Provided analysis regarding schedule delay and cost overrun issues on an NGL processing project involving construction of central process and satellite facilities. Performed the analysis work on behalf of an owner to identify the magnitude and compensability of potential affirmative claims against a prime contractor.

Offshore Oil and Gas

Russia

On behalf of an owner, evaluated its position for a claim against the EPCM contractor for mismanagement, cost overruns, and delays on the performance of a cost reimbursable contract to design and build an offshore oil and gas production facility. Performed a schedule and cost variance analysis to identify where delays and cost overruns occurred and the allocated causes for such overruns against the owner and the contractor.

Gas, Gasification, GTL, LNG, and NGL

Illinois

Retained by the owner of a natural gas liquids extraction and fractionation plant involved in arbitration with an electrical and instrumentation contractor. Analysis and opinions provided included contract review, determination of breach of contract, delay analysis, and calculation of cost reimbursements owed to the contractor and damages incurred by the owner.

Offshore Oil and Gas

Texas

Performed an analysis in support of an owner’s claim against an international EPC contractor’s performance, delays, and $100 million cost overrun regarding a Spar production facility that was fabricated in Finland for installation in the Gulf of Mexico. Issues involved material delays, welding rework, quadrupling of labor man-hours, wet mating of hard and soft tank/truss, delay, liquidated damages, conversion of contract issues, and related damages.

Refineries, Petrochemical, and Chemical

Louisiana

On behalf of a contractor, analyzed an EPC contractor’s change order and delay claims on a chemical plant project.

Transportation

New Mexico

On behalf of a concrete bridge contractor, analyzed key impacting events that delayed and extended drilled foundation pier/shaft work by a subcontractor on a highway bridge in southeast New Mexico. Quantified and allocated delay caused by the subcontractor that resulted in the owner assessing liquidated damages against the concrete bridge contractor. Prepared two expert reports and testified at deposition in preparation of a jury trial. Both parties settled the dispute after depositions.

Power

Florida

An EPC contractor designed and supplied two 300 MW Circulating Fluidized Bed (CFB) boilers to replace oil and gas-fired boilers, as well as boiler islands on two units. Engaged to prepare a schedule delay analysis related to a claim filed for an equitable adjustment of the contract price on behalf of the EPC contractor against the owner. The project team later made a presentation for mediation to the owner on the EPC contractor’s behalf.

Gas, Gasification, GTL, LNG, and NGL

Kansas

On behalf of an owner, analyzed alleged deficiencies in the design of a petroleum coke gasification and syngas plant that resulted in change orders, delay, and loss of productivity claims totaling $25 million against the owner of a refinery. The project involved the relocation of a coal gasification facility from California and redesign of the plant based on petroleum coke feed.

CONTACT US

Experience Matters

Our experts are ready to help.

Our extensive international experience includes large, complex, grass roots, revamp, and reconstruction projects incorporating conventional-phased, fast-track, and EPC turnkey concepts.